Newsgroups:
sci.physics.plasma
From: FAIRFAX@CMOD2.PFC.MIT.EDU
Subject: Alcator
Highlights, Aug. 4 & 11
Alcator
C-MOD Weekly Highlights
August
4, 1994
The maintenance/repair period is continuing. Work on the new
design for the
coax buss is proceeding.
Prototype components incorporating the new design,
which features a
more compliant head piece for the inner
coax, have been
fabricated and will be tested. Additional calculations to
verify the design
are in progress.
While the bus work proceeds,
additional maintenance activities are also being
carried out. The vessel
heaters, which are normally inaccessible, are
undergoing a thorough
inspection.
In-vessel work this week has included removal of a set
of tile modules on the
inner wall, in preparation for installation of new
halo current diagnostics.
In addition, we will replace a few of the tiles
with specially prepared
"tracer" tiles, containing a thin
coating of tungsten under an overcoating of
molybdenum. This work, being
carried out in collaboration with Sandia, will
investigate the erosion and
re-deposition of molybdenum during high-power
operation.
A
shot from the June, 1994, run period has been selected for additional
analysis
using the DEGAS code; this work is being carried out by Daren Stotler
of
PPPL. The particular shot,940623028, was part of a divertor studies run,
and
includes density and temperature profiles at the target plate and
fast-scanning
probe profiles in the main chamber, as well as a complete set of
H-alpha
data. This shot was a low density discharge on which divertor
detachment
did not occur.
C.H. Ma of ORNL is working at MIT this week,
preparing his Faraday rotation
diagnostic. This diagnostic works in
conjunction with our existing Two-Color
Interferometer (TCI), and will be
used to measure the current density profile.
All of the main components of
the rotation experiment are now installed on the
laser table, and
rotations of the order of 2 degrees have been successfully
detected using
a polarization rotator installed on the table.
Professor Ian
Hutchinson has returned from his sabbatical at JET. Martin
Greenwald is
participating in the ESNET Steering Committee Meeting in New
Mexico.
___________________________________________________________________________
Alcator C-MOD
Weekly Highlights
August
11, 1994
The maintenance/repair period is continuing. Fabrication
drawings for a
full-scale prototype of the new design for the inner coax
conductor have been
approved and released to the vendors. Rough cut parts for the prototype coax
have
already been produced.
Cleanup and resurfacing of the terminal
plate for the OH2L coil has been
completed. All three coils in the OH
stack have been electrically tested
(rung) at 600 volts.
All
400 vessel heaters have been checked out and are working correctly.
TRANSP
is now being run in "production" mode. Analyses of about a dozen
shots
from the 1993 and 1994 operating campaigns have been produced, with
ten more
in progress. So far the
analysis is being carried out for ohmic discharges.
Analysis of ICRF
heating shots, using the TRANSP ICRF package, will begin
shortly.
In
the course of attempting to resolve a small discrepancy (at the level of
a
few percent) in our magnetic analysis, we have determined that the
vacuum
vessel exhibits a small magnetic permeability. Our control system
and
equilibrium analysis appear to be robust against this effect, as
expected since
these depend principally on measurements of the fields and
fluxes in vacuum
inside the vessel. The discrepancy shows up primarily
when the vessel currents
inferred from the analysis are compared to those
expected, or equivalently
when magnetics signals are compared with
expected values based on integrating
the circuit equations using measured
coil currents.
Dr. Roger Richards from ORNL is back at MIT this
week, continuing
installation work for his laser scattering
experiment.