Newsgroups:
sci.physics.plasma
From: IRBY@CMOD2.PFC.MIT.EDU
Subject: C-MOD Weekly
Highlights
Alcator
C-MOD Weekly Highlights
September 15, 1994
Assembly of the OH2L coax is now well
underway. The operations remaining
include bending, vacuum impregnation,
and fitup to the OH2L coil terminal
block. The feltmetal sandwich material used between the coax and
terminal
components is now being produced at a rapid pace. Finally, components
for the OH1 and
OH2U coax are being completed. Only the
the OH2L
coax is on the machine assembly 'critical path'.
The
upgraded power supply for the third ICRF transmitter has
arrived and is in
position. This system, along with a fourth system
still requiring
modification, will be used to drive the PPPL antenna.
Some minor
changes to the cryo system have been made.
The flapper
valve that regulates cryostat pressure by controlling
the GN2 flow
through the bus tunnel has been replaced. The old valve was subject
to icing on
its bearing surfaces. We have also
moved all the
pressure transducers used to monitor nitrogen pressure in
the
coils to an easy to reach position, away from the control
valves.
This change should make the pressure readings more reliable.
Miklos
Porkolab and Paul Bonoli were at PPPL this week for a
meeting on ITER
RF. Earl Marmar and Jim Irby were also
at PPPL for
a meeting on ITER diagnostics.