Newsgroups:
sci.physics.plasma
From: BLIP@CMOD2.PFC.MIT.EDU
Organization:
MIT
Subject: Alcator C-Mod weekly report 11/9/94
Alcator C-MOD Weekly
Highlights
November
9, 1994
Pumpdown of the machine was accomplished last week. Several large leaks were
found in
reflectometer feedthrus at A-port.
These were blanked off and the
pumpdown proceeded again before the
weekend. Over the weekend a 60-hour
bake
of the machine was conducted up to temperatures of 120 degrees
C. Leak checking
resumed once the
base pressure was low enough. Argon was
used in conjunction
with the RGA due to the large deuterium
background. A smaller leak was found
at a periscope at A-bottom (small one).
That is being pumped while the
leak check continues today. The base pressure is currently in the 10^-7
range.
After the leak check finishes the machine will be let up to air to
fix any leaks tomorrow. Then
baking will then resume.
All power systems have been tested under
PLC control at low power. Further
tests at high power will be started tomorrow. Hybrid control will
be reimplemented next week with the
high power testing repeated.
The Thomson scattering systems are
mostly operational. A in-cell
calibration
will proceed when the leak check is completed and the
calibration source
can be put in place. Machine interfaces are being
tested
(through the shot cycle). New baffle assemblies in both the
vertical
and horizontal ports were installed during the vacuum break.
CRYO is
up and operational. Cooling was active
during the bake keeping
the coils at -25 degrees C. The Alternator is up and running as
well.