Newsgroups:
sci.physics.plasma
From WOLFE@CMOD2.PFC.MIT.EDU Tue Jul 18 09:28:20
1995
From: WOLFE@CMOD2.PFC.MIT.EDU
Organization: MIT
Subject:
Alcator C-Mod Weekly Highlights
Alcator
C-MOD Weekly Highlights
July
17, 1995
Scheduled maintenance and upgrade activities are proceeding
on Alcator C-MOD.
Planned machine inspection is now essentially
complete. All of the TF coax
bolts
have been checked and torqued to specified torque. The high strength
bolts
at the first and last turn were also torqued to spec. All OH and EF
upper connections were checked for torque,
frayed cables, loose LN2 lines,
insulation, etc. The OH-1 and OH-2U
felt-metal connections were examined
with the borescope. These all
looked good. The OH-1 and OH-2U thermocouple
and voltage sensing leads
were tested and checked out ok.
All Cryo system inspections are
complete. We found no problems with
TF
cooling except that arms which had been observed to cool more slowly
were
found to have longer feedlines. These feedlines have been shortened
and are
now closer to the feed manifold.
Both E- and F-port
inner/secondary seals have been inspected and the extensions
installed. Leak checking of the interseal space has
been completed.
The upgrade of the EF2 supplies is well
underway. The plan is to move TMX
modules
from the present EF4 to increase the current capability on EF2, and
use
supplies from Alcator C, presently at LLNL, to drive the EF4 coil.
Rewiring
of TMX supplies is complete. Control
circuitry changes are also
complete.
Changes to the PARAGON control program are in progress. The new
EF4 power supplies from LLNL
are now packaged for shipment. We will
be
sending two engineers to LLNL for inspections and to monitor
loading
procedures. Fabrication of the power room DC bus to connect the
new EF4
supplies is underway.
F-port outer divertor module has
been removed for checkout/repair of divertor
probes. All halo current monitoring shunts are now
out of the machine. These
are being
replaced with new halo rogowski coils at each of the outer divertor
modules.
The floor mounting plates will be machined to accommodate these coils.
One
such plate has been modified, and a test fitup performed to verify the
procedure.
The G10 insulation plate covering TF bus at A-port has been improved
and
re-installed. A-port
diagnostic stand extension for the edge Thomson
scattering has been
completed and is ready for installation.
Roger Richards of ORNL was
at M.I.T. working on his ion-scattering diagnostic.
Optical benches have
been installed in the cell and diagnostics lab for this
experiment.