Newsgroups:
sci.physics.plasma
From WOLFE@CMOD2.PFC.MIT.EDU Tue Aug 15 16:14:33
1995
From: WOLFE@CMOD2.PFC.MIT.EDU
Organization: MIT
Subject:
Alcator C-MOD Weekly Highlights
Alcator
C-MOD Weekly Highlights
Aug.
15, 1995
The scheduled maintenance period continued on ALcator C-MOD
last week.
Good progress toward readying the facility for the fall
operating campaign
continues.
Tile cleaning, module assembly,
and staking of tile holddowns is going
well. Fit-up and re-installation of
tile modules is proceeding.
The E-port ICRF antenna backplane is
back in the machine. E-port horizontal
flange has now been
reinstalled.
The gas feed flange for the boronization system has
been installed, and
fabrication of the gas system is underway.
Work
is proceeding on the EF4 supplies, including connection of the new bus
work
and cleanup of the converter cabinets and transformers returned from
Livermore.
The CO2 laser for the Two-Color
Interferometer (TCI) arrived back from the
vendor. This is a sealed laser
which had been sent out for re-charging
following completion of the last
campaign.
The optics head for the edge Thomson scattering system
was found to be leaking
following the final welding procedure in New
Jersey. Laser welding to seal up
the
leaks is being carried out at a local shop. The in-vessel mounting
bracket
for this module has been successfully fitted up in the machine.
New windows were installed for a prototype frequency-doubled
YAG
interferometer, which will be installed for density measurements along
a
tangential path at the midplane.
Steve Golovato was at GA last week to participate in the
DIII-D experiments to
match C-MOD dimensionless parameters for a test of
the validity of
dimensionally similar scaling studies. The corresponding
C-MOD experiments
were carried out in May, and the DIII-D run attempted to
match the C-MOD
dimensionless parameters as well as possible. Power scans
were carried out
using both NBI and RF heating which should provide a good
comparison with
C-MOD data.