Newsgroups:
sci.physics.plasma
From WOLFE@CMOD2.PFC.MIT.EDU Wed Jan 10 12:02:57
1996
From: WOLFE@CMOD2.PFC.MIT.EDU
Organization: MIT
Subject:
Alcator C-MOD Weekly Highlights
Alcator
C-MOD Weekly Highlights
Jan. 9, 1996
Operation of Alcator
C-MOD resumed last week with a half-day run to establish
a baseline
condition prior to boronization. A campaign of boronization
wall-conditioning,
using the electron cyclotron discharge cleaning (ECDC)
technique, was then
begun.
Testing of the EF1 power supply with the new transformer was
successfully
completed. This upgrade will allow higher voltages to be
applied to the EF1
coils with a resulting improvement in plasma control.
A short clean vent (He backfill) was performed to remove an
obstruction from
the Thomson scattering beam baffles. The obstruction was
identified as a hose
clamp buckle which had apparently been accidentally
left inside the vessel
during the last major opening.
A short
(half-day) run was scheduled and carried out on Friday in order to get
a
good baseline of machine operation before boronization. After a round of
helium
ECDC, a series of five standard fiducial shots were run, followed by a
density
scan. RF power up to 2MW was injected. One lithium pellet shot was
taken,
resulting in a PEP mode.
The diborane (10% B2D6, 90% He) bottle was
delivered on Friday and placed in
our external toxic gas storage cabinet.
Following a full run-through of the boronization procedure, using
helium gas,
the diborane bottle was installed in the in-cell diborane
cabinet. This
procedure was performed under controlled access by two
people wearing Self
Contained Breathing Apparatus (SCBA). While the
diborane is in the cell,
restricted access procedures are in effect.
The boronization campaign was begun on Sunday and is continuing
this week. The
procedure being employed is similar to our normal ECDC,
using the
helium-diborane mixture as the working gas. The toroidal field
is swept to
move the resonance layer across the chamber. Unlike our usual
procedure, the
discharge is pulsed at a 50% duty cycle to facilitate more
uniform deposition
of boron on the walls. Once a satisfactory boron layer
has been deposited,
tokamak operation will resume, beginning with a
repetition of the baseline
shots taken last week.