Newsgroups:
sci.physics.plasma
From IRBY@CMOD2.PFC.MIT.EDU Wed Mar 20 21:57:35
1996
From: IRBY@CMOD2.PFC.MIT.EDU
Organization: MIT
Subject:
Alcator C-MOD Weekly Highlights
Alcator
C-MOD Weekly Highlights
March
20, 1996
Alcator C-Mod is
currently up-to-air, but will be pumped
down again today so that further
ECDC can be done to remove boron hydride
deposits on the outer wall and
lower divertor cover plates.
These
deposits formed during boronization at radii beyond which the
ECDC
resonance was allowed to extend.
The ECDC resonance will
now be run well out into the horizontal
port extensions to break up
the hydrides and allow them to be pumped
away. In-vessel work has
therefore
been delayed. However, a great deal of other scheduled work has
begun.
Transmitter #3 and #4
installation is moving rapidly now
that access to the power room is
routine. Both crowbar cabinets
have
been moved into the power room where modifications will continue.
The
conduit for the #3 transmitter has been installed and HVDC and
control
cables are being run. Water cooling
systems and their
associated control and power components are being
mounted on their
stands. The fixed
frequency cavities have been removed from the
driver units in preparation
for the tunable ones to be supplied as
part of our PPPL
collaboration.
Cooling of our
TF magnet during high field runs slowed down
our shot cycle considerably
during the last run campaign. We are
now
making modifications to the cryo system to speed up the cooldown
time. New valves will be added to the TF magnet
manifold so that warmer
parts of the magnet can be selectively cooled at
higher LN2 pressures.
The new system design is complete and major
components are on order.
Modifications to the LN2 storage tank have begun
which will provide
higher LN2 flow rates to the pump. A new LN2 pump has been
installed, and
the old one sent out to be reconditioned.
We
have also continued work on our diagnostic stand extension.
Most
components have been fabricated and installation will begin next
week.
This extension will provide much needed new floorspace in the cell
for
future systems such as the diagnostic neutral beam (to be installed
in
collaboration with the University of Texas).
Evolution of the finite-element model of the inner and
outer
divertor continues. This
model allows us to determine forces on the
divertor plates with various
assumptions about halo and eddy current
distributions. Input of magnetics data from a C-Mod
disruption
is being incorporated into the model. This effort is required
to
ensure reliable operation of our new inner and outer divertor hardware
at up
to 2 MA of plasma current.
Paul Bonoli is at the
Sherwood meeting this week.
Martin
Greenwald, Amanda
Hubbard, and Darren Garnier attended the TTF workshop
in Philadelphia last
week and gave talks. Alberto Loarte is
visiting
from JET to collaborate on our divertor physics modeling
effort. Don McDonald
and Bob
Phelan visited from Boulder Metric, Inc. to discuss techniques for
improved
absolute calibration of detectors from mm to visible wavelengths.