Newsgroups:
sci.physics.plasma
From IRBY@CMOD2.PFC.MIT.EDU Wed Apr 3 11:00:13 1996
From:
IRBY@CMOD2.PFC.MIT.EDU
Organization: MIT
Subject: Alcator C-MOD
Weekly Highlights
Alcator
C-MOD Weekly Highlights
April
3, 1996
In-vessel work
began this week. A video survey of
the
internals was made and an inspection of the first wall
hardware
carried out. The inspection of the first wall showed no broken
or loose
tiles, or bent support plates.
Therefore changes made to the
support structure during the last up
to air were adequate for
our
current operating parameters. Before
coming up to air,
glow discharge cleaning was performed to further reduce
the level
of boron hydrides in the machine. This process required the
construction of a glow discharge
electrode and switchable ballast
resistor bank. A discharge was easily
maintained down to pressures
of approximately 2mT where the electrode
potentials could be kept
in the 300 to 400 volt range. These potentials are believed to be
high
enough to break down the heavier borane compounds.
The alternator inspection continues. The flywheel lifting
frame has been installed and the lower
flywheel bearing removed for
inspection.
Some repair work will be required on the lower bearings.
Ultrasonic
tests of the bore and UT have continued and are nearing
completion.
The HVDC conduit and cables for ICRF
transmitter #4
have been installed.
The 480 VAC control power has been run to
the FMIT driver
distribution system for transmitters #3 and #4
as well as to the water
cooling systems. The 4-port switch is
in
house and being prepared for installation. This switch allows the
transmitters to be switched between a
dummy load and the antennas.
Support
legs and trusses have been installed for the diagnostic
stand
extension. Planning continues for
moving racks and hardware
away from near the machine and onto the new
stand.
Vacuum system work, PLC
programming, and instrumentation
installation for the cryopump prototype
continues. Cooldown cycle
tests
and pumping speed measurements will be made shortly.
Jon McChesney visited from General Atomics
this week and
gave a talk. Ian
Hutchinson is in Washington for the IAEA paper
review.