Newsgroups:
sci.physics.plasma
From IRBY@CMOD2.PFC.MIT.EDU Tue May 28 21:37:21
1996
From: IRBY@CMOD2.PFC.MIT.EDU
Organization: MIT
Subject:
Alcator C-MOD Weekly Highlights
Alcator C-MOD Weekly Highlights
May 28, 1996
Our maintenance period continues. Work proceeds on the divertor,
the
divertor cryopump, RF systems, TF cooling, and diagnostic upgrades.
Welding of the divertor support plates is
more than 60% complete.
All machining operations are complete on 20% of
the plates. Outer
divertor modules
can be re-installed invessel beginning late this week
or early next
week.
The invessel fitup of the
divertor cryopump is going well. A
minor
change to the mounting hardware will be needed to leave more space
for a flux
loop that runs under the divertor module. The pump vacuum
feedthrough mated
properly with its flange. Measurements have been made that were needed to
complete
fabrication of the 300K shield. A test
fitup of the GH outer
divertor module, which covers the cryopump, will be
done as soon as the module
is ready for installation. Following the fitup, the pump will be
returned to
the vacuum test stand where PLC program development can
continue, and more
pumping speed tests can be made.
The closed loop de-ionized water cooling
system for the new
transmitters is nearly finished. The PLC interface control and
indicator
wiring is complete. Work
has begun on modifications to the new transmitter
driver cabinets. Support hardware for the new 9" coax
runs is being
installed.
PLC
control cabling to the new TF control valves is complete. PLC
programming and debugging can now
proceed.
All alternator
instrumentation has been re-installed and checked,
and the alternator is
ready for operation. It will be brought
up to
speed over the next two weeks.
Work
continued on several other engineering and diagnostic systems.
The ceramic
tubes that will house the retro-reflectors for the new tangential
interferometer
were sent out to the vendor where the retro-reflectors will be
installed. Stainless steel standoffs for the new glow
discharge system are
now fabricated and will be sent out for an
electrically insulating spray
coating.
The electrical feedthroughs for the glow discharge system are now
being
installed on D-top flange. A final
design review of the C-port
horizontal flange modifications was held and
changes to the flange can
now begin.
A-top flange is being modified for installation of a new RF
probe.
Brian LaBombard, Garry McCracken, and
Bruce Lipschultz were at the
PSI meeting in France last week. Yuichi Takase was in Garching at both
an
ITER design review meeting and the European Coordinating
Committee
Meeting on Fast Wave Heating and Current Drive.
Contributions
to the PSI meeting included:
Invited paper --
Experimental
Investigation of Transport Phenomena in the Scrape-off Layer
and Divertor,
B. LaBombard, J. Goetz, I. Hutchinson, D. Jablonski, J. Kesner,
C. Kurz,
B. Lipschultz, G.M. McCracken, A. Niemczewski, J.L. Terry.
Contributed
oral --
Modification of the Divertor Detachment Onset Density
B.
Lipschultz, B. LaBombard, G.M. McCracken, J. Goetz, H. Ohkawa,
Y. Takase
and J.L. Terry.
Contributed posters --
A Comparison of
Impurity Screening Between Limiter and Divertor Plasmas in
the Alcator
C-Mod Tokamak, R.S. Granetz, G.M. McCracken, F. Bombarda,
J.A. Goetz, D.
Jablonski, B. LaBombard, B. Lipschultz,
H. Ohkawa,
J. Rice, J.L. Terry, Y. Wang.
Screening of
Recycling and Non-Recycling Impurities in the Alcator
C-Mod Tokamak,
G.M. McCracken, R.S. Granetz, B.
Lipschultz, B. LaBombard,
F. Bombarda,
J.A. Goetz, D. Jablonski, S.
Lisgo, D. Jablonski, H. Ohkawa,
J. Rice, P.C. Stangeby, J.L. Terry, Y.
Wang.
Local Impurity Puffing as a Scrape-off Layer Diagnostic on
the Alcator
C-Mod Tokamak, D. Jablonski, B. LaBombard, G.M. McCracken,
S. Lisgo,
B. Lipschultz, I.H. Hutchinson,
J.L. Terry, and P.C. Stangeby.