Newsgroups:
sci.physics.plasma
From IRBY@CMOD2.PFC.MIT.EDU Tue Jun 11 22:19:05
1996
From: IRBY@CMOD2.PFC.MIT.EDU
Organization: MIT
Subject: Alcator C-MOD Weekly Highlights
Alcator C-MOD Weekly Highlights
June
11, 1996
The up-to-air
continues. Progress has been made on
the outer
divertor, diagnostics, RF systems, and alternator.
The remaining work on the outer divertor
is now mainly a cleanup
and reassembly activity in preparation for final
installation of the
ten modules.
Fitups of the newly machined plates indicate that the
final
installation will go smoothly. The
divertor cryopump is being
re-installed in the vacuum test stand for high
pressure pumping
speed tests.
Installation of the pump in C-MOD is scheduled for early
next week
following installation of its associated divertor module.
We have received the phase shifter and
stub tuner for the new
RF transmitters.
The stand for these new components is being designed.
The cavities
from transmitter #3 and #4 have been removed in preparation for
installation
of the tunable cavities when they arrive from PPPL. High voltage
stress cones are being installed in the high
yard for the new RF systems.
The
pressure transducers for the new TF upper arm cooling manifold
were
finally delivered and are now installed.
Paragon programming for the
new manifold is complete.
Strain gauges are being installed on the
vessel inner wall. This
installation
follows an intensive period of development and testing that was
required
to produce gauges capable of operation during very high dB/dt
conditions.
This new diagnostic will greatly enhance our ability
to understand the
effects of disruptions on the vacuum
vessel (an ITER relevant
activity).
A test of a
prototype discharge cleaning electrode went well.
The electrode was run at
full current for several hours in our vacuum test
stand. It remained at an allowable temperature, and
provided a uniform glow
throughout the chamber. Two electrodes are planned for installation
during this
break. A test fitup of the electrodes
invessel also went
well, and the vacuum feethrough has been leak checked
and is ready for
installation.
The
startup procedure for the alternator has been completed
to the point of
running the rotor at low speed. Full
speed operation should
be obtained in a few days.
Joe Bartolick, Boris Grek, and Dave
Johnson are here from PPPL working
on the edge Thomson scattering system
(PPPL collaboration). The fiber
links for the computer and GPIB are
installed and working. The
polychromator detector system has been
operated, and the signal fibers are
being installed. The fiber bundles
have been checked for broken fibers and
orientation inside the machine.
The final laser mirror mount is installed
and the alignment beam has been
brought as far as the internal input aperture.
The fast alignment fibers
are installed and have been checked.
Bill
Dorland, from the IFS at the University of Texas, spent two days
here to
begin a collaboration on transport modelling.
C-MOD data will
be compared to results of the IFS-PPPL transport
theory.
Earl Marmar was at
Berkeley last week at a review on inertial
confinement heavy ion beam
drivers. Yuichi Takase attended the
third
meeting of the Alternate
Concepts Panel (sub-committee of FEAC SciCom)
in San Diego. Vinny Bertolino, Joe Bosco, and Sergey
Andreyev visited
PPPL last week to discuss diagnostic neutral beam power
systems and controls,
and the RF components due to arrive at MIT next
month as part of the
PPPL collaboration.
Tom Fredian and Josh Stillerman are at the Korean
Basic Science
Center upgrading the center's MDS data system to MDSplus
and providing
training for the new system.