Newsgroups:
sci.physics.plasma
From IRBY@CMOD2.PFC.MIT.EDU Tue Jun 18 20:09:08
1996
From: IRBY@CMOD2.PFC.MIT.EDU
Organization: MIT
Subject:
Alcator C-MOD Weekly Highlights
Alcator C-MOD Weekly Highlights
June 18, 1996
We have begun re-installation of the outer
divertor modules.
This process will continue for approximately the next
ten days. Five
out of ten modules
are now installed. Invessel work
associated with
diagnostic upgrades is now determining the module
installation schedule.
Work on
other invessel systems continues. The
strain gauges have been
installed on the inner vessel wall, and the
associated cables are being
run.
The diborane feed tubes have been machined and welded, and clamps
for
holding it to the vessel are being machined. Clamps for the glow
discharge coax feeds are complete. A prototype glow discharge insulator
was
hi-potted successfully. The remaining
insulators will be in-house
by the end of the week.
Stress cones have been installed on all
13.8 kV AC and high voltage
DC connections associated with the new
transmitters. Upgraded
transformers
have been installed in the driver cabinets.
The
new TF upper arm cooling valves have been tested and are
operational
through the PLC. The new Paragon screen
is complete and
tested. The cryo
valve box and LN2 lines are being insulated and
sealed in preparation for
the GN2 purge.
Work on the edge
Thomson scattering continues both at MIT and
PPPL. Analog fiber links have been installed
between the laser room and
cell.
The D to A module for the HeNe dither drive was tested,
but a
failed HeNe power supply kept a system test from occurring. The YAG beam
enclosure
is nearly complete, as is alignment of the polychromator. The
signal
fibers are mounted and ready to be mated to the polychromator. An
invessel
inspection of the fibers was done to confirm their orientation in
their
holder. A permanent protective housing for these fibers is under
construction.
TORVAC control modifications for the new
forepump are complete
and the PLC/Paragon software is being updated. The new pump will allow
one pumping
stack to operate independently of the other.
This change is
needed to provide better differential pumping for
the RGA and to allow
higher throughput for boronization.
Analysis of data from the last run
campaign continues. Central
impurity
toroidal rotation during ohmic discharges has been
measured from the
doppler shifts of x-ray emission lines. The magnitude
of the rotation is a
few x 10^4 m/s, in the direction opposite to the
plasma current, and is in
qualitative agreement with the predictions of
neo-classical theory.
Earl Marmar was at PPPL last week
attending the FESAC Scientific
Issues
Subcommittee (SciCom) meeting.