Newsgroups:
sci.physics.plasma
From IRBY@CMOD2.PFC.MIT.EDU Tue Jul 9 21:03:34 1996
From:
IRBY@CMOD2.PFC.MIT.EDU
Organization: MIT
Subject: Alcator C-MOD
Weekly Highlights
Alcator C-MOD Weekly Highlights
July 9, 1996
We are now working to close up the vessel
and pump down
by the end of this week.
A great deal of work has been done in the
last few days including
diagnostic calibrations and alignments, and
installation of glow
discharge, tangential interferometer, shutter, edge
Thomson scattering,
and divertor gas puff components. We
have also begun
to bring engineering systems such as bus instrumentation,
vessel heaters
and thermocouples, oxygen monitors, and access control back
on-line.
The alternator was
brought up to full speed last week. We
found that the rotor alignment was still not
acceptable, and we are now
working
with GE (prime contractor for the inspection) to make
adjustments.
Difficulties in the installation of the
support studs for the
cryopump and its 300K shield have delayed this
project somewhat. These
issues are
now resolved, and we are proceeding as quickly as possible.
The glow discharge coaxes have been
installed invessel and fitups
of the the electrodes completed
successfully. Final installation
will
occur as soon as the cryopump installation is complete.
Ferrites have been installed on one of
our X2274 final amplifier
tubes which had exhibited high-frequency
parasitic oscillations.
Similar problems were observed in X2274 tubes at
PPPL and were corrected
in the same way.
If this fix is successful, other tubes will be
checked for
parasitic oscillations and fixed if necessary.
This change will
make operation possible with any of our spare
final amplifier tubes.
During the last week, we have also continued installation
of new RF
transmitter components.
The final amplifier cavity for transmitter #3
has been assembled
and placed in position in the power room.
Mounting
configurations for coaxial switches, the dummy load, and
tuners are being
finalized.
Work
continues on various aspects of the Texas/MIT collaboration.
Vinny
Bertolino and Joe Bosco continued their visit at the
University of Texas
Fusion Research Center last week. They
spent most
of their time discussing documentation with both current and
former
FRC staff members. They now
feel confident that some of the major DNB
components are sufficiently well
documented for disassembly to begin.
Working with FRC personnel, we have
also developed a shipping schedule
and work list that will deliver DNB
components to MIT as quickly as available
manpower will allow. FRC scientists have also begun work on the
optics
needed to couple their 1st harmonic O-mode radiometer to our
ECE
beamline. This radiometer will
be used to study electron temperature
fluctuations.
We were delighted to learn that four
invited talks will be given
on Alcator C-Mod results at the next APS
meeting in Denver:
P. Bonoli, Electron heating via Mode Converted
Ion Bernstein Waves in the
Alcator C-Mod tokamak
G. M.
McCracken, Impurity Screening in Ohmic and H-Mode Plasmas
in the Alcator
C-Mod Tokamak
J. Rice, Observations of Parallel and Perpendicular
Impurity Transport
from Alcator C-Mod Plasmas
Y. Takase,
ICRF-heated Enhanced Confinement Modes in the Alcator C-Mod
Tokamak