From:
IRBY@CMOD.PFC.MIT.EDU
Subject: Alcator C-MOD Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: M.I.T.
Alcator C-MOD Weekly Highlights
January 21, 1997
Reassembly of Alcator C-Mod
continues. The lower PF
coil
package is in place and aligned, and the mounting plates are being
installed. The OH2L coax has also been installed and
resistance checks are
underway.
All upper PF coils are in place, and alignment of the coils
is
proceeding. Hi-Pot and ringing tests
are being performed on each coil
as they are positioned, as are flow rate
tests of coil cooling passages
and fittings. Many of these tests will be repeated as major components
are
added to the assembly.
Work
on power systems last week began to concentrate of improvements
to the EF4
supplies to provide more reliable operation with the magnets
in the
parallel configuration. The EF4 PLC
software was upgraded, new reactors
for the supply were ordered, and work
has begun on improving the response time
of the EF4 fault detection
circuits.
Work on the crowbar
circuits and associated trigger units for the
new RF transmitters is
moving rapidly. The new high voltage
trigger
transformers are complete and ready for testing. Fitup of coax between the
drivers and
finals and the finals and the couplers is nearly complete. High
yard maintenance continues as we
checkout and adjust Ross bottles, breakers,
and control circuitry that
will supply both the old and new transmitters.
We have begun to work on layouts, schematics, and design
details of
the DNB regulator/modulator and capacitor bank. Power distribution work
continues.
Our machine shop is working at full
capacity producing components
needed for the new invessel diagnostics
discussed last week.
Brian
LaBombard visited the University of Texas in Austin last
week, and
presented a talk on C-Mod SOL studies.
He also discussed
possible probe experiments for the upcoming run
campaign with
Roger Bengtson and Dave Winslow.