From:
IRBY@CMOD2.PFC.MIT.EDU
Subject: Alcator C-MOD Weekly Highlights
Organization:
M.I.T.
Newsgroups: sci.physics.plasma
Alcator C-MOD Weekly
Highlights
January 28, 1997
Reassembly of Alcator C-Mod was delayed
somewhat this week
when the EF1L coil high voltage ringing test did not
not meet
specifications. Breakdown
occurred between the coil terminal and one of
the newly installed mounting
plates. To fix this problem the
mounting
plate was removed, the coil insulation was repaired, and the edge
of the
mounting plate was machined back away from the coil terminal
block. The
repairs are complete,
the coil has been rung successfully, and we will soon
continue
reassembly.
All work on
transmitter #1 switchgear is complete, and we are
now making similar
modifications to the switchgear for the #2 transmitter.
Work on the
crowbar system and triggers for the new transmitters continues
as does
fitup of the new coax. Coax runs have
been layed out from the final,
to the phase shifter and stub tuner, and
then to the entrance to the cell.
The required components are being
fabricated at PPPL. All fault
detection
circuit boards for the new transmitters have been
completed.
Work on the power
systems concentrated on new overvoltage protection
boards for the EF4
supply. These boards use breakover
diodes to detect
overvoltages on the EF4 bus and trigger crowbar
protection circuitry.
The power systems group is also pushing forward with
DNB installation.
The new grounding system for the DNB is complete, specifications
for the
modulator/regulator are being generated, and the holding tank for
oil used by
the DNB supplies has been specified and is in
fabrication.
Upgrades to the
glow discharge system are underway. The
maximum
resistance selectable under PLC control has been increased. This change
will add some protection
for invessel components during glow discharge
conditioning. Hall current sensors have been added to the
glow system
so that the current to each glow electrode can be measured
without
regard to bias resistor selection. The fabrication of shutters for
protecting the new
tangential two-color interferometer (TTCI) mirror and
the re-entrant
window used by our wide angle camera is complete.
Assembly of the the TTCI
shutter is also complete and cycle tests should
begin soon.
Dave
Terry was at U Texas last week discussing DNB issues. Earl
Marmar attended the latest FESAC meeting in San Diego
where
discussions where held on the upcoming FESAC ITER review. Franco Porcelli
of the University of
Torino, Italy, just visited C-Mod. Dr.
Porcelli
is involved in a collaboration on sawtooth activity involving
C-Mod staff
and members of the PSFC theory group. He also presented an
informal seminar
"Comments on X-point Dynamics". Dave Johnson, Boris Grek, and Joe
Bartolik
from PPPL are at MIT this week working on the edge Thomson
scattering
system.