From:
IRBY@CMOD.PFC.MIT.EDU
Subject: Alcator C-MOD Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: M.I.T.
Alcator C-MOD Weekly
Highlights
February 11, 1997
Reassembly continued this week on Alcator
C-Mod. The lower TF
arms are now
installed and preparations are being made to move the
vessel from the
assembly stand back to the lower dome in the center
of the cell. Another set of hi-pot, continuity, ground
fault, and
resistance checks of coils, coaxes, heaters, thermocouples, and
OH
diagnostics has been successfully completed. As soon as the machine
is back in position on the lower
dome, we can resume invessel work.
We
continue to make progress on the design of the DNB
accelerator power
supply and modulator/regulator. Designs
for the
new crowbar system required to protect the DNB beamline are also
being
developed. We have installed
temporary power to the variac control
cabinet for low power testing of DNB
supplies. Many improvements have
been
made to the magnet power systems over the last few months, so a very
careful
and detailed checkout of all the supplies will be required. This process
began this week with work
concentrating on the EF4 supply. Work
on the
new transmitters continues.
Layout of the coax runs is complete and
coax components are being
fabricated at PPPL. The first of four
new crowbar
trigger units for the new transmitters is complete. RF tuner and phase
shifter PLC
interface wiring has been finished.
Reconditioning of the dummy
loads for transmitters 1 and 2 is
complete.
A great deal of work
has now been completed on new invessel
components. New diode arrays and telescopes for making
high spatial
resolution measurements of the plasma edge have been
fabricated. The
new shutter for
protecting the tangential interferometer mirror has
undergone an extensive
cycle test successfully and is now being prepared
for installation
invessel. The capillary needed to
supply gas to the
new scanning gas probe has also undergone an initial
cycle test of
acceptable duration, but will be improved somewhat and
tested again.
A meeting of our
Program Advisory Committee was held last
Thursday and Friday at MIT. The committee consisted of Stewart Prager
(chairman, U. of Wisc),
Joel Hosea (PPPL), Dave Hill (GA), Karl Lackner
(Garching), Ben Carreras
(ORNL), Richard Hazeline (U. Texas), Ted Straight
(GA), and Douglass Post
(PPPL). Rostom Dagazian represented
DOE.
Ken Young (PPPL) and Tom Simonen (GA) attended as observers.
Talks
on physics results and plans were given by both MIT staff and
some of our
collaborators; Bill Rowan and Ron Bravenec (U Texas), Randy
Wilson and
Cynthia Phillips (PPPL).
DOE
has requested that we write quarterly reports rather than
the monthly ones
we have produced for the last few years.
These quarterly
reports are
posted on the web at
http://cmod2.pfc.mit.edu/cmod/quarterly-reports/quarterly-reports.html