From:
IRBY@CMOD2.PFC.MIT.EDU
Subject: Alcator C-MOD Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: M.I.T.
Alcator C-MOD Weekly
Highlights
February 25, 1997
Several days were lost on the reassembly
schedule last week after
an inspection revealed some spring plates to have
been installed incorrectly.
These plates insure that proper pressure is
applied to the TF finger joints,
which is critical to magnet
performance. The machine was lifted
from the
lower dome and placed back on the assembly stand for access. Following
re-installation of the spring
plates and another complete set of inspections,
the machine is now back on
the lower dome.
We continue to
make progress on the DNB installation.
Riggers have
been contracted to move the Tara gyrotron power
supplies from their
current location to the power room. In preparation for the move, we have
drained
the oil from the supplies and cleared the area around the
supplies for
better access. The beamline itself has
now been moved to a
new lab area where it will be assembled and intial
tests begun.
A great deal of
work was done last week preparing the EF4 supply for
the next
campaign. The new overvoltage board was
installed and tested,
as was the
latch circuitry that interfaces with the PLC. Fuses and gates
have been checked on the converter and
crowbar circuits. The new fast type
I fault circuit has also been
installed. The supply has been
hi-potted
and the regulator has been checked (integrator, clamps, faults,
feedback
V and I, lockout etc). Cabling has been replaced and rerouted in
some
locations to improve noise immunity and eliminate possible ground
loops.
The first crowbar
trigger circuit for the new transmitters is
complete. Three other units are being fabricated. Switchgear for the
#3 transmitter is
complete and tested, and we are completing work on
the switchgear for the
#4 transmitter. We continue to work on
control
circuitry for the new transmitters, and are working with PPPL to
complete
the new coax runs.
The
prototype cryopump has been installed inside a mockup of the
outer
divertor on our vacuum test stand. An
extensive set of pumping tests
have been carried out. The pump easily handles gas loads larger
than those
expected on C-Mod.
Pumping speeds of 1000 l/s have been measured during
deuterium gas
puffs with peak pressures of 25 mTorr.
Analysis
of C-Mod data continues. Toroidal
rotation velocities
greater than 1e7 cm/sec (200 kR/sec) have been
observed in the highest
H-factor H-mode plasmas (ICRF only), in the
co-current direction. When Ip
is reversed, the rotation also reverses
direction. Spatial scans
indicated
the rotation velocity is highly peaked near the magnetic
axis. These
measurements were made
by observing the Doppler shift in X-Ray line
radiation from highly
stripped Argon.
Mike McCarthy
from PPPL visited last week to discuss upgrades
to the reflectometer
system. Schedules and work plans were
developed for
MIT and PPPL with the goal of installing the reflectometer
for the next
run campaign with improved
fluctuation measurement capability and frequency
stability.
Steve Wukitch went to PPPL last week to
participate in mode conversion
experiments.