From:
IRBY@CMOD.PFC.MIT.EDU
Subject: Alcator C-MOD Weekly Highlights
Organization:
MIT
Newsgroups: sci.physics.plasma
Alcator C-MOD Weekly
Highlights
March 4, 1997
All TF upper arms and all but three
vertical legs are now installed,
and the installation of spring plates is
underway. Following boroscope
inspections,
hi-pots, coil ringing test, and clean up, the cylinder
will be installed
later this week.
Contractors
arrived today to move the 100kV power supply from
storage into the power
room. As mentioned last week, this
supply will be
used to provide ACCEL voltage for the DNB. Other DNB
related work included
more development of mod/reg plans, and addressing
issues involving
the crowbar needed for the new supply. A simulation of the
new supply,
mod/reg, and load is being developed so that specifications
for the filter
bank can be drawn up. We also continue
to ready the
new DNB lab area where the beamline will be assembled and
tested. A
safety review has been
carried out of the new area, and specifications
developed for ventilation,
power, and interlocks. Work on the DNB
control
system also continues.
The
power systems group is now focusing its effort on the
TF supply. Checking this supply is a major activity,
just one aspect of
which is the testing of 480 SCR driver boards.
We continue to make progress on the new
transmitters. All safety
interlocks
on transmitter #3 driver cabinet have
been tested. Filament
and bias supplies for the IPA, driver, and FPA, on
transmitter #3 have been
tested at
full voltage but not at full power.
Work continues on the crowbar
trigger circuits and the crowbars
themselves. John Gumbas from PPPL
is
visiting this week to help with the installation of the new
transmitter
driver units. PPPL is
nearly finished with the coax sections we will
need for the new RF
transmission lines.
One of our
LANL collaborators, Dr. R. Maqueda, was here last week to
check on the
fabrication and assembly of the IR periscope system that we are
building
to specifications supplied by the LANL group.
This new periscope
will view down into the divertor from a vertical
port.
Bruce Lipschultz was in
San Diego last week at the DIIID
PAC meeting. Earl Marmar was in San Diego at the ITER Joint Work Sight for
a
meeting on progress in diagnostic development.