From:
IRBY@CMOD2.PFC.MIT.EDU
Subject: Alcator C-MOD Weekly Highlights
Organization:
MIT
Newsgroups: sci.physics.plasma
Alcator C-MOD Weekly
Highlights
March 25, 1997
Reassembly of Alcator C-Mod
continues. All horizontal port
extensions
have been installed and helium leak checked through their
secondary
seals. As mentioned last week, the port
extensions had to be in
place before some invessel installations could
proceed. Installations
such as the
divertor prototype cryopump and the JHU divertor spectrometer
are now
progressing rapidly. The rf antennas
and feedthroughs have
also been installed. Work on the curved bus and coaxes is nearly complete,
as is
installation of all the LN2 cooling lines.
The magnet cooling PLC has
been brought back into operation so that
all the LN2 valves could be
checked for proper operation, and cooling
paths verified. All heaters,
thermocouples,
OH flux loops, and OH position sensors have been checked for
proper
operation now that the tokamak is complete.
The final hi-pot and
ringing tests required before the machine is
sealed inside the cryostat
are underway. The lower cryostat is ready to be
raised into position, after
which the vacuum hardware on the lower
vertical ports can be installed.
The torus pumping station has been moved
back into the cell and installed
on the port extension.
The DNB fabrication continued with design
work on the ACCEL supply
control system, and successful no-load tests on
both the ACCEL and the
Arc/Filament/Snubber supplies. We can now refill these supplies with
oil
and begin filtering and degassing it in preparation for bringing
them
back online.
Work
continues preparing the magnet power supplies for
operation. OH2 upper and lower converter cabinets have
been checked
and made ready for operation as have the IOC/current feedback
boards.
The EF1 upper and lower converter cabinets and IOC/current
feedback
boards were also checked and are ready for operation. In addition,
crowbar firing levels have
been adjusted to specification.
The
crowbar trigger circuits for the new transmitters have been
tested and are
being calibrated. Preparations continue
on the
crowbar cabinets with installation of the new trigger circuits
expected
soon. Work continues on
water cooling, control, and transmission
systems. Safety interlocks and
bias and filament power supplies have
been tested on transmitter #4. The coax components fabricated at PPPL
have
arrived.
During the past month,
the collaborators from UT-FRC have been
concentrating on preparations for
the spring campaign. Design of
the
turbulence probe diagnostic was completed, and the vacuum hardware
required
for C-Mod pumpdown was received at MIT along with all required
CAMAC
equipment. The ECE
radiometer which will be used by the Auburn/MIT/UT
collaboration for
electron temperature profiles and fluctuations is now at
MIT, also with
all its required CAMAC equipment.
Testing of components
for two DNB diagnostics, BES and CXRS, is
planned. The equipment for
both of these is in the final stages of preparation
at UT.
Work continues on
several diagnostic systems.
Thermoelectric coolers
for stabilizing the reflectometer Gunn diode
frequencies arrived at PPPL and
layout drawings have been generated for
installing them at MIT. We have
begun
to discuss with PPPL software and hardware changes that should much
improve
the operation of the reflectometer system.
Newly recoated optics have
been installed on the
two-color-interferometer diagnostic, and improvements
made to the
collimator mounts. This system is being
brought back on line
now so that alignment can begin as soon as we have
access to the torus. A new
95 microgram Cf252 source has arrived from Oak
Ridge. It will replace the
old
source which had decayed to the 18 microgram level. The new source
will allow us to achieve a good
signal-to-noise level during our neutron
calibration in much less time. In
order to measure the D0 Lyman alpha line,
molecular deuterium lines, and
the strong carbon and nitrogen lines
above 1200 Angstroms, the long
wavelength end of the spectral range of our
VUV spectrograph is being
extended from 1100 to 2200 Angstroms. In
addition, an in situ calibration
facility for the spectrograph has been
developed and is being installed
and tested.
We continue to
analyze spectroscopic rotation data.
The argon
toroidal rotation radial velocity profile has been used
to determine the
radial electric field during better H-mode and enhanced
D-alpha H-mode
discharges. At r/a = .3, the field is 300 V/cm, about a
factor of 2 larger
than the ion diamagnetic term.
Mark May and Sean Regan are here this week
from JHU to complete
installation of their divertor spectrometer.
Bob Granetz was in Moscow last week for
the ITER MHD Expert Group
meeting.
Earl Marmar was in San Diego for a meeting of the FESAC ITER
review
committee, which was held at UCSD.