From:
IRBY@PSFC.MIT.EDU
Subject: Alcator C-MOD Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: MIT
A lcator
C-MOD Weekly Highlights
April 15, 1997
Work on Alcator C-Mod this week
concentrated on bringing up the
engineering systems required to run the
experiment. Vessel heaters and
thermocouples,
cryo system, bus instrumentation, ECDC, pulsed gas system,
and secondary
seal pumps are coming back online.
After the first pumpdown
last week, several days were devoted to
finding and fixing leaks. We are
now
ready to begin the vessel bake.
The final magnet hi-pots have been completed
successfully and the
magnets have been reconnected to the power supplies. We
are preparing to do low power tests into the magnets to
check out the
supplies, controls, interlocks, and bus
instrumentation. All TMX
contactors
have been reconditioned and reinstalled.
Work continues on bringing up the new
transmitters and transmission
lines.
All RF power supplies have been tested and calibrated. All interlocks
with
the exception of the FPA interlock have also been tested. Coax components
needed to couple power
to the antennas are now being assembled and installed
in the cell. We are wrapping up work on the high voltage
switchgear.
Installation of the
DNB power supplies continues.
Reassembly
of the Mod/Reg which provides switching and regulation
for the accelerator
voltage began.
The major emphasis for the DNB control system design is
currently
the fast interface between the main control system, the ACCEL
supply, and
the crowbar which is required for protection of the beamline in
the event
of a fault. The background activity of
filtering and degassing the
oil for the arc/filament/snubber and ACCEL
supplies is nearly complete.
We
continue to install and test diagnostic systems. The new
time-of-flight diagnostic has been moved into the
cell and is being
installed. The
lower mirror for the TCI system is in place and we are
about to start the
alignment process. The tangential
charge exchange
diagnostic has been moved into the cell and
installed. The mirrors and
beamline
for the X-point Thomson scattering system are now going back onto
the
machine.
John Gumbus is
visiting from PPPL and will assist with assembly and
testing of the new
transmitters. Rick Maqueda from LANL
has been
at MIT for the last week assembling, testing, and preparing
to
install an IR periscope/camera system on C-Mod. The IR image has
been
transferred over 5 m to the camera and is of very high quality. Jim
Weaver from the University of
Maryland is on-site and will remain here
through the next run campaign. He
will operate the University of Maryland
high resolution spectrograph. Dave Johnson, Boris Grek, and Joe
Bartolick
from PPPL are here this week to re-install the X-point Thomson
scattering
and do a Raman calibration.
Ian Hutchinson, Steve Wolfe, Miklos Porkolab, and Earl Marmar
were at
the Field Work Proposal meeting in Germantown last week. John Heard, one
of our collaborators
from Auburn who is now permanently on-site here
at MIT was at the EC10
Conference in Holland. Martin
Greenwald, Joe
Snipes, and Steve Wolfe are in San Diego at an ITER Expert
Group Meeting.