From:
IRBY@CMOD.PFC.MIT.EDU
Subject: Alcator C-MOD Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: MIT
Alcator C-MOD Weekly
Highlights
April 21, 1997
The Alcator C-Mod vacuum vessel is now
being baked. Cooling of the
magnets
has also begun since they must be cooled with liquid nitrogen to an
average
temperature of -25C to protect them from the high temperatures.
In
addition, we have begun the slow cooldown of the domes and cylinder which
are
made up of about 175,000 lbs of stainless steel and require several days
to
cooldown to operating temperature. The
bake will last most of this week,
after which ECDC cleaning of the vessel
walls will begin. We continue to
install
and align diagnostics.
Much
progress was made this week on the new RF systems. Coax
installations both in the cell and the power room are
nearing completion.
New ignitrons for the crowbar circuits arrived and are
being installed.
Water cooling systems for the new transmitters are in
operation and their
temperature interlocks have been checked. HV anode cable conduits are being
installed. The FPA cavity for transmitter #4 has been
assembled and
cavity position indicators for the driver/IPA have been
calibrated.
Power system
checkouts continue. The bus instrumentation
system
is now operational, some of which is being used to control the
magnet LN2
cooling. Preparations
are being made for a review of changes
to the power systems to be held
early this week. Low current tests
of
power supply operation into the magnets are scheduled to begin
later
this week.
We
continued the installation of the DNB power supplies. Reassembly
of the Mod/Reg continued, and we began to develop
the design changes that
are required to incorporate the new ACCEL
supply. Control system design
on
the fast interface between the main control system, the ACCEL supply, and
the
crowbar continued.
Those of you
interested in viewing the new invessel diagnostics
might check out the
inspection photos at:
http://www.pfc.mit.edu/cgi/cmod_images?name=invessel/
Rick Maqueda continued his visit from LANL
last week working to
install the new IR periscope. Joe Bartolick, Boris Grek, and Dave
Johnson
from PPPL successfully completed the Raman calibration of the X-point
Thomson
scattering diagnostic last week. John
Gumpus and Gerd Schilling, also
from PPPL, continued their work with our RF group helping to bring
the
new RF systems online.