From:
IRBY@CMOD.PFC.MIT.EDU
Date: Tue, 19 Aug 1997 8:19:46 -0400 (EDT)
Subject:
Alcator C-MOD Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator C-MOD
Weekly Highlights
August
18, 1997
The
Alcator C-Mod maintenance period continued last week with
work on the
alternator, DNB, and RF systems.
Analysis of data from the
last run period continues.
All wedges have been taken off the
alternator rotor, and the
field copper is being removed. The coil cleanup crew is onsite and
will
begin cleaning the field copper as soon as they can complete the setup
of
their equipment.
Assembly of
the DNB beamline in the test lab is complete.
The
beamline has been supported in a configuration appropriate for installation
on
C-Mod. Quotes on components for the low
capacitance transmission line
that will connect the beamline to its power
supplies were received,
including those for ductwork, insulators and
standard transition boxes.
Location for the transmission line was
determined, and design of the
supporting trestles has begun. Development of the PLC interface for
the
vacuum system continued, and PARAGON screens on vacuum system status
are
now available. Modifications
to the waveform generators used with the arc
and mod/reg supplies were
completed and tested. We began
development of an
improved diagnostic system for collection of the
thermocouple and secondary
emission data required to measure beam
footprint, neutralization efficiency,
and progress on beam
conditioning. System requirements were
determined, the
data acquisition system design was completed, and
appropriate CAMAC modules
have been located.
A detuned dummy load connected to FMIT#1 has been used to
simulate
operation when the antenna match to the plasma load is imperfect
due to
changing plasma conditions.
As was expected, the final stage gain is phase
dependent. When operating at maximum source power (2
MW), an increase in
gain can result in a screen overload fault, and the
transmitter trips
off temporarily.
The transmitter arc detectors (there is another pair
of arc
detectors located near the antenna) will be tested using the detuned
load
as well.
Further analysis and
testing of FMIT#4's Uptegraff power supply has
found a failed capacitor in
one phase of the supply. Previously the
problem
was thought to be blown diodes in one of three secondary legs, but
modelling
the power supply with failed diodes could not reproduce the
measurements.
When the failed capacitor was included in the model, the
model and experimental
measurements were in agreement.
Analysis of the 40 MHz RF Testing and
Conditioning experiments
has shown central direct electron heating
consistent with excitation of mode
converted Ion Berstein waves. The
peaked profile has a full-width half-maximum
of < 0.2 r/a. The analysis was done with by break-in-slope
analysis
of the 9 channel grating polychromator ECE diagnostic. The fraction of
total power deposited
into electrons as determined by this method is <0.25.
TORIC simulations
indicate that approximately 50% of the power is absorbed
directly by
ions.
On Thursday of last week
the vessel was backfilled with
hydrogen to complete the Core Thomson
Scattering calibration.