From:
IRBY@PSFC.MIT.EDU
Date: Tue, 26 Aug 1997 07:53:25
EST5EDT4,M4.1.0,M10.5.0
Message-ID:
<009B957D.98797920.23@woods.uml.edu>
Subject: Alcator C-MOD Weekly
Highlights
Newsgroups: sci.physics.plasma
Organization: MIT
Alcator C-MOD Weekly
Highlights
August
25, 1997
The
Alcator C-Mod maintenance period continued last week with
work on the
alternator, DNB, Power, and RF systems.
Analysis of data from
the last run period continues.
Rapid progress is being made on the
alternator repair. All
field coil
copper has been removed from the rotor, and much of it has
been
cleaned. Clean up of the rotor forging
has begun, and ultrasonic
testing is expected to begin in the next few
days.
Assembly of the DNB
beamline vacuum system was completed and control
cables installed. During tests of the backing pump, the
beamline was partially
evacuated.
Control cables and connection points in the DNB vacuum system
controller
were identified for use by the PLC interface.
Testing of the
CAMAC modules for the thermocouple/secondary
emission data acquisition
system began at UT-FRC and will be shipped to
MIT as soon as the testing is
done. Several options for the isolation
amplifier system were identified, and
these are being compared. Control wiring for the variac cabinet
was
completed. Work has started on
the control wiring for the magnet supply.
We
have begun work on the TF power supply aimed at determining
the cause of
junction overtemp trips during the last run campaign. The
overtemp circuits are being fed simulated TF waveforms
in an attempt to
reproduce the trip conditions.
Maintenance on FMIT#1 and #2 is
continuing. Both transmitters are
undergoing
testing into an detuned dummy load, and the arc detection system in
the
power room is being tested. New tuned
arc detectors have been designed.
The tuned arc detectors will be
installed on D and E ports to isolate
the signal from each antenna. This upgrade will allow the arc
detector
to better discriminate against power radiated from one antenna to
the
other, which has often caused erroneous trips of the arc detection
circuits.
The demodulator calibration is nearing completion and the
H-probe has
been repaired and awaits pressure testing. The PLC wiring for FMIT#3
and FMIT#4 is
continuing and the 120 V power to the new racks in the control
room has
been upgraded.
J. Snipes, in
collaboration with King-Lap Wong and Guoyong Fu of PPPL
is making
comparisons between experimental data and rough calculations of the
Toroidal
Alfven Eigenmode physics. Short bursts
of fluctuations have been
observed on poloidal field pick-up coil signals
during strong ICRF heating
applied early in the current rise. The oscillation frequency varies from
about
200 to 400 kHz in approximately 15 ms with a very sharp
frequency spectrum
(FWHM of less than 10 kHz, 1 ms window). The comparisons
with TAE theory
suggest that a fast ion tail driven by the central resonant
H minority
ICRH could be responsible for driving TAE modes under these
conditions. Measurements with a charge exchange analyzer
indicate that there
was indeed a strong H ion tail present out to energies
of at least 100 keV
during the relatively low density (1 x 10^20 m^-3)
ramp-up phase of the
discharge with strong ICRF heating. TRANSP calculations with FPPRF also
indicate
tail energies of about 100 keV.
Craig
Petty of DIII-D spent two days at the PSFC discussing analysis
of
dimensionless scaling experiments.
Approximately half the time was
spent going over analysis of
DIII-D/C-Mod non-dimensional identity L-mode
experiments which were
conducted last year, and half on future plans.
These
included dimensionless scaling experiments of L and H-mode
confinement,
particle (impurity) transport, L/H threshold, MHD, and
turbulence. Dr. Petty
also
presented a seminar on results of non-dimensional scaling experiments
and
implications for future devices.