Date:
Tue, 17 Mar 1998 8:16:10 -0500
From: IRBY@CMOD.PFC.MIT.EDU
Reply-To:
IRBY@PSFC.MIT.EDU
Message-ID:
<980317081610.51013586@CMOD.PFC.MIT.EDU>
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT
Plasma Fusion center
Alcator
C-Mod Weekly Highlights
March 16, 1998
The Alcator C-Mod maintenance period continued last week
as
we concentrated on disassembling the machine. More igloo blocks,
cabling, diagnostics, and ports were
removed as we prepared to lift
the cylinder. The top dome cover was removed on thursday giving us access
to
the top TF arms and core. Small amounts
of copper and carbon tracking
radiating out from the A-right TF leg were
found. However, most of the
debris
is probably contained within the cylinder.
We hope to have
the cylinder off early this week, at which point we
will also be able
to remove TF arms and legs for detailed
inspections. We have also found
a
small crack on one of the TF core fingers which we cannot properly
inspect
until the spring-plates and upper arm are removed.
First invessel access occurred last Tuesday after a
several
day long room-air purge to eliminate the effects of residual
boron
compounds. Detailed radiation and video
surveys were done before
general access was allowed. Following the surveys, calibrations of
several
of the invessel diagnostics were performed. An extensive set of digital
pictures
detailing hardware on the outer wall was also taken. These pictures
will appear on our WEB site soon.
The development of the diagnostic neutral
beam continued with
progress on the Mod/reg system, PLC control, data
acquisition, and diagnostics.
The crowbar trigger and control system
isolation transformer/power
distribution for the Mod/Red is now
complete. Design began for the grid
drive
circuits for the power tetrode, and HV cables were installed to the
test cell.
PLC programming for control of the DNB waveform generators was
completed.
These waveform generators provide timing for power supplies and
process
gas feed during the interval in which the beam is generated. The
two camac crates, one for timing
and acquisition of engineering data,
the other for beam diagnostics, were
connected to their buses and
successfully tested. The camac data acquisition modules for the
DNB
profile diagnostics were installed in their final locations and
provided
with triggers and clocks that are distributed from the master
DNB
decoder. DNB diagnosticians completed
their optical designs for
MSE and CXRS.
The optics were developed using commercial optical
design
packages. The diagnosticians are now
involved in arbitrating
the use of space on the flange and in recommending
modification of
structures near the machine to provide adequate access for
the
diagnostics.
Work in
the power systems group last week included continued
development of new
over-voltage protection boards. Checks
on the
calibration of the bus instrumentation continued. Power systems
group personnel also
began to work on DNB related projects last week.
This change will
certainly move this major project along more quickly.
The RF group has continued working on
exploring the upper frequency
limit of FMIT#3, antenna disassembly,
porting ACCOME to the VAX, and
advanced tokamak scenario modelling. The maximum frequency obtained
to date
is 76.9 MHz. Approximately half of the
ACCOME modules have been
modified to compile properly on a VAX Alpha
machine. Advanced tokamak
scenario
developmental work has been done for a single null, high
beta, high q
equilibrium.
Last week Boyd
Blackwell from Australian National University visited Tom
Fredian and Josh
Stillerman to discuss plans for upgrading their MDS data
acquisition
system to MDSplus. Romik Chatterjee
from the University
of Texas visited on Friday to work on some hardware
for the O-mode
radiometer.
Dave
Johnson from PPPL visited last week to direct calibrations
of the X-point
Thomson scattering system. Ben Welch
visited from the
University of Maryland to direct calibrations of various
visible
light spectroscopic systems.