From:
IRBY@CMOD.PFC.MIT.EDU
Date: Tue, 31 Mar 1998 11:02:25 -0500
Reply-To:
IRBY@PSFC.MIT.EDU
Message-ID:
<980331110225.22a2b3e7@CMOD.PFC.MIT.EDU>
Subject: Alcator C-Mod
Weekly Highlights
Organization: MIT Plasma Fusion Center
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
March 30, 1998
All TF legs and upper arms were removed
last week, and the machine
was moved to a support stand in the southeast
corner of the cell. This
move was
required before the lower arms could be removed. Inspections of the
upper arms indicate the need to replace
feltmetal in many locations,
particularly on the inner most pads. We are currently reviewing the
early
analysis of the finger joints in this location and also extending
this
analysis with both analytic models and the better numeric tools now
available. Inspections of the lower arms that have been
removed thus far
reveal very little feltmetal wear. Understanding this upper-lower
asymmetry
has of course become a very important task for our analysis
group.
We have continued
preparations for the installation of the new RF
antenna. FMIT#3 was tested at 78.5 MHz with an output
power of 1.5 MW into
a dummy load.
This frequency will be used with
the new PPPL antenna during
our next campaign. The coax transmission lines from the transmitters to the
cell
are being modified to link up properly with the matching network to
be
installed near J-port. Dr. Paul Bonoli
and Ken Takase have been working on
porting ACCOME to the C-Mod ALPHA
Workstations. This work was
motivated
partially by planned changes at NERSC where they plan to remove
from service a
compiler which was used by ACCOME. The equilibrium solver,
lower hybrid and
neutral beam modules have been ported. Work remains on debugging the
lower
hybrid module and writing an IDL post processor.
The antenna work at PPPL continues as well. The straps have
been plated and the Mo
Faraday rods have been bent and stress
relieved. The rods are currently being brazed, and this process is
expected
to take 2 weeks. The rods will then
need to be coated with
TiC. Some
of the back plane parts have been plated and are being
assembled for
electrical testing and measurements of the completed
antenna. These tests and measurements will provide
the remaining data
necessary to design the resonant loops.
Work continued on the diagnostic neutral
beam. The ground pad for the
mod/reg
was built and installed, nonconducting hardware was installed on
mod/reg
HV cable docks, and high voltage cable was run from the mod/reg to
the
cell wall. The fiber optic transmitter
and receiver board testing was
completed.
Construction and testing of the thermocouple system for
measurement
of the unneutralized component of the beam was completed from
the signal
conditioning chassis input to the CAMAC modules. Work continued
on fiber optic communication for the arc/fil/snubber voltage feedback,
monitoring
and fault systems, the NWL controls, and the DNB timing system.
The HV
ductwork termination box at the cell wall was installed for cut-to-fit
matching
to the existing cell wall penetration.
Preliminary
analysis of the C-Mod/Jet dimensionless identity
experiments shows rather
good dimensionless agreement in the transport
parameters. However, it now appears that the shapes run
on JET in the shots
most similar to C-Mod were somewhat different from
those previously planned.
Therefore more analysis is needed to
investigate the extent to which shape
differences have compromised the
experiment or may explain the observed
differences in ELM behaviour.
During ELMy bursts, fast dips (20 ~ 30
microsec) have been observed
on our ECE grating polychromator (GPC)
signals, which are correlated
with D_alpha and magnetic bursts. As the density increases, the dips
have
been observed even on the inner-most GPC channels. One good candidate to
explain such
dips is a density cutoff effect. When
a narrow, sharply
localized edge density, high enough, but not thick
enough to cutoff X-mode
second harmonic waves is assumed, evanescent
wave-like features will occur.
Careful analysis of these wave effects has
begun.
Ricky Maqueda from LANL
visited C-Mod week-before-last to work on the
IR imaging periscope. It was found that the presumed boronization
coating
on the sapphire window was in fact composed of small chips that
had
broken off the edges of the ZnSe elements. Modifications to the periscope
are being planned to fix this
problem for the next campaign.
We
also plan to modify the view of the periscope to image the
divertor
surface below the outer nose. Finally,
the Kodak fast
framing camera hardware was removed from the C-Mod cell and
shipped to Los
Alamos so that the intensified imager can be serviced.
Jim Terry attended the AIP
Topical Conference on Atomic
Processes in Plasmas which took place at
Auburn University from March 23-26.
He presented a very well received
invited talk - "Study of
Volume
Recombination and Radiation Opacity Effects in Alcator C-Mod Plasmas".
Paul
Bonoli attended the Sherwood theory meeting last week.