From:
IRBY@CMOD.PFC.MIT.EDU
Date: Tue, 21 Apr 1998 21:08:55 -0400
Reply-To:
IRBY@PSFC.MIT.EDU
Message-ID:
<980421210855.22a6473f@CMOD.PFC.MIT.EDU>
Subject: Alcator C-Mod
Weekly Highlights
Organization: MIT Plasma Fusion Center
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
April 20, 1998
We continue preparations for the repair of
the TF magnet. The
hydraulic
soldering fixture required to attach the feltmetal to the magnet
finger
joints has been setup and is in operation.
New laser cut feltmetal is
in-house and will be used for soldering
tests over the next couple
of days.
The machining of the new TF vertical leg plates is complete,
and
work on the new TF horizontal arm plates will begin shortly. Detailed
analysis of the forces and
thermal effects at the finger joints during
high field shots has made good
progress.
We continue to debug the crowbar problem on FMIT#4 which
is
limiting the power at 78 MHz to about 500 kW. It is uncertain at this point
whether the problem is in the
crowbar circuit itself or if it indicates a
real fault in the RF section
of the transmitter (tube for example).
PPPL has
extended the services of an RF engineer, Chris Brunkhorst,
to work with us
on this problem. Progress was made last week on testing
the control boards
for the new transmitters. A group of 12 boards need to be tested before we
can begin
full operation with the new antenna.
The 9" coax installation has
progressed as far as it can until
the DC breaks have been modified to limit
RF leakage, and the new
modification tested.
Last week
we reported that the 4-strap antenna Faraday shield
rods had developed a
cracking problem around the threaded ends.
PPPL has investigated further
by pull and shock testing the rods. A
single
Faraday rod is made of three pieces: one straight piece with a
threaded
end (center post) and two bent rods with threaded ends. The three
pieces are brazed
together. All rods passed the pull
test, but the bent
rods failed the shock test. The failures show no signs of ductile
deformation before
breaking which suggests the material is brittle at
room temperature. The proposed short term solution is to
remove the
threaded TZM and replace it with Inconel. In parallel PPPL is also
investigating
replacement of the TZM rods with copper coated inconel.
PPPL has continued
to prepare the RF test stand for antenna electrical
characterization and
testing. Gerd Schilling (PPPL) has
continued to
develop a resonant loop model for the new antenna.
Conditioning of the oil in the DNB Mod/Reg
isolation transformer
continued after observing a test breakdown of 35
kV. On the arc/filament
/snubber
supply, we made progress on the circuit design for the interface
to the
master control logic (MCL) unit. The
required number of fiber optic
transmitter boards was completed, some
fiber optic transmitters and receivers
were installed, and associated
fiber optic links were routed and connected.
Work on fault circuitry
calibration for the arc/filament/snubber voltage
feedback and monitoring systems
continued. The hardware and
software
for the CAMAC timing of the DNB during the plasma discharge was
completed
and tested under software control through the output of the
CAMAC modules.
Attention here has now shifted to distribution of other
control functions
between PLC and CAMAC.
The modified clock board was installed in the MCL
and the input
connectors for the new timing signals to the existing chassis
and
interconnecting wiring were completed.
Larry
Owen and Ben Carreras of ORNL were here much of the week
assembling data
and running models with the goal of calculating the neutral
profiles in
C-Mod, in particular prior to the L-H transition.
We forgot to mention in a previous weekly report that on April
2nd
Miklos Porkolab visited the Magnetic and Laser Fusion Groups at
LANL
and gave a seminar on the MIT PSFC Programs. He also discussed collaborations
with
LANL personnel, particularly in the MHD modeling area where they are
completing
a new nonlinear MHD code, called NIMROD, under the leadership
of Allen
Glasser.