Date:
Mon, 4 May 1998 20:25:27 -0400
From: IRBY@CMOD.PFC.MIT.EDU
Reply-To:
IRBY@PSFC.MIT.EDU
Message-ID:
<980504202527.29611524@CMOD.PFC.MIT.EDU>
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT
Plasma Fusion Center
Alcator
C-Mod Weekly Highlights
May 5, 1998
We continue to develop the inductive
heating technique for
replacing TF feltmetal. A test fixture with an array of thermocouples
and associated
data acquisition equipment has been fabricated and is being
used to
determine temperature profiles during the soldering process.
Different
coil geometries will also be tried so that an optimized heating
profile
can be determined. The TF core has been
repositioned on a new
stand so that cleanup and replating activities will
be easier to perform.
A detailed survey of feltmetal thickness on the
upper and lower horizontal
arm inner joints was finished. The upper horizontal arm feltmetal
averaged
.004" thinner than the lower, consistent with the more advanced
wear found
there.
We
continued to progress in the development of the DNB for C-Mod.
The fault
circuitry in the arc/filament/snubber voltage feedback and monitoring
system
was completed and calibrated. The breakdown voltage for the oil in
the
tank shared by arc/filament/snubber supplies was found to be 20 kV and
conditioning
of the oil was begun using the same techniques as for the
accelerator
supply and for the Mod/Reg isolation transformer. The design
of the logic boards in the arc/filament/snubber interface
to the MCL was
completed.
Calibration and testing of the control system for arc detection
was
begun. A review of the integration of
the beam firing and conditioning
cycle with the C-Mod firing cycle was
held to assist in finalizing the
remaining hardware and software
required.
We continue to look
for the cause of the FMIT#4 crowbar. We
have
tested the driver into a dummyload without a fault. This test suggests the
problem is in
the final stage. We will begin
disassembly midweek for a visual
inspection. If no arc indications are
found upon inspection, we will replace
the tube with a spare and test the
transmitter again. This change
should
allow us to determine if the arc is in the tube or the cavity. We have also
begun testing the control
system for FMIT#3. Testing of control
boards also
continues.
Martin
Greenwald, Ian Hutchinson, Earl Marmar, Spencer Pitcher,
Miklos Porkolab,
Joe Snipes, and Steve Wolfe attended the Next Step
Conference in Madison
Wisconsin last week. Miklos Porkolab
gave a
presentation on ATBX, or Advanced Tokamak Burning Plasma
Experiment,
a reduced size, 50% cost, version of ITER.