From:
IRBY@CMOD.PFC.MIT.EDU
Date: Tue, 12 May 1998 8:52:16 -0400
Reply-To:
IRBY@PSFC.MIT.EDU
Message-ID:
<980512085216.25a00165@CMOD.PFC.MIT.EDU>
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT
Plasma Fusion Center
Alcator
C-Mod Weekly Highlights
May 11, 1998
A review of the TF magnet was held at MIT
on Wednesday, May 6th.
Phil Heitzenroeder and Peter Bonanos from PPPL,
Phil Edmonds from U.
Texas and ITER, Herb Becker from Sigmilon, and Bruce
Montgomery from
MTechnology were on the review committee. A report will be put together by
the
review committee chairman, Peter Bonanos.
Presentations on the
magnet, cooling system, power system, thermal
and electromagnetic analysis,
and proposed fault and repair scenarios were
given.
We continue to make
procurements, develop procedures, make soldering
tests, build new
inductive heating coils, design fixturing, and disassemble
horizontal
magnet arms as we proceed with the magnet repair. The latest
inductive heating tests were quite successful in
that we both obtained good
data from a thermocouple array arranged on the
test fixture, and were also able
to solder four feltmetal pads onto a
finger joint. A 100 kW inductive
heating
unit is being procured for installation at MIT. Cleanup of the TF core
is also
proceeding. Finally, a testing station
capable of quantifying
feltmetal under a variety of temperatures,
pressures, and current densities,
while sliding is being assembled.
Recent invessel work has been devoted to
making accurate
measurements of the relative position of the outer
divertor modules using
a gauge that was employed for this same task in
1995. Similar measurements
were made at that time before the outer
divertor was strengthened with
solid pins and stronger mother bolts. These measurements will be compared
for
any changes in position. A
test fit-up of a prototype divertor
'flapper' valve was performed on nine
of the ten outer divertor
modules. The unit was found to clear all
existing in-vessel hardware
including the fast-thermocouple array at
F-port. Limiter locations were
also
measured. The FG limiter was
found to be slightly tilted left to right (2 mm).
Both the FG and GH
limiters have been removed so that new diagnostics can be
added and old
ones reworked where needed. The outer
divertor module at
F-port was removed from the vacuum vessel. This unit contains the embedded
fast-thermocouple
and the outer divertor Langmuir probe arrays.
Repairs
of minor damage to the probe sensors and cabling that
occurred over the
last two run campaigns will now proceed. William Carmack from INEEL has
continued
to collect dust from invessel during this up-to-air. A careful
sweep of the wall was done shortly after we came
up-to-air with a 0.5 um
filter. Clusters
of small, spherical, molybdenum particles were found along
with some glass
fibers associated with insulation from cabling for some of
our
diagnostics. A new sweep under the
outer divertor modules has just been
completed and the samples have been shipped
out to INEEL.
We continued our
progress on the DNB. We began
development of the
VAX software that will detect the C-Mod State and
facilitate limited control
of the beam. This software will be combined
with existing timing software to
create a package that will integrate the
beam firing and conditioning cycle
with the C-Mod shot cycle. Work continued on these safety interlocks
and the
interface of the Master Control Logic (MCL) system to the PLC and
to the
arc/filament/snubber supply.
The prototype grid drive board for the Mod/Reg
was completed and is
being tested. The construction of the
Mod/Reg voltage
divider assembly was completed, and its performance is
being optimized.
Conditioning of the oil in the tank shared by the
arc/filament/snubber
supplies continued with modest improvement in the
breakdown voltage. The
arc/filament/snubber
cables were terminated at the
snubber and an
insulating support
for their continuation to the source in the test lab was
fabricated. Calibration and testing of the control
system for the arc
notcher was completed.
PLC programming for control and monitoring of the
suppressor supply
and switch, safety interlocks, magnet supply and Mod/Reg
were begun.
All parts were ordered for the F-port
flange which will be the
location of the DNB and various other
diagnostics. An assembly and
installation
procedure was developed for the periscope, reciprocating
turbulence probe
guide tube, and ECE mirrors which are located together in
a very compact
grouping near the bottom of the flange.
These and other
aspects of the F-Port flange construction, and the
DNB diagnostics will be
reviewed on May 20.
We continue to make progress on RF projects. FMIT#4 has
been disassembled. Initial inspection of the output cavity has
found no
arc damage; however, a more complete inspection is underway. We
intend to use a spare tube to test
whether the tube is bad or the
arc is in some other part of the
transmitter. Preparations for installation
of the DC breaks have been
completed. The support brackets are
in
place and the shielding material is on hand. PPPL has offered to supply a
female-to-female 9"
coaxial elbow to keep the plumbing job moving forward.
The backup Inconel
shield for the PPPL antenna is out for bids.
This bid
is being pursued in case the proposed design changes to
the TZM shield fail to
correct the shock failure problem. Assembly of the antenna in the test
stand
continues.
Paul
Bonoli has been successful in modelling advanced tokamak
single-null
scenarios with ACCOME. He has
instituted an error minimization
technique which eliminated a convergence
problem. Previously, the
code
would begin to converge upon a solution after several iterations
but begin
to diverge upon subsequent iterations.
Resulting
equilibria from the new error minimizations have been
cross checked
by Jesus Ramos using the CAXE code. We have also begun to work on a
patch
to connect TORIC with TRANSP until TORIC is fully integrated
with TRANSP
(PPPL project undertaken by Dan Clark under the supervision
of Cynthia K.
Phillips). This patch will simply
import a
TORIC deposition profile into TRANSP. We are implementing this patch
because the SPRUCE code in
TRANSP has difficulty with off-axis (r/a >
0.5) D(H) minority
heating. This patch has the
disadvantage that fast
particle effects upon wave damping will not be
accounted for
self-consistently.
However, given the high densities at which C-Mod normally
operates,
this is a minor effect and we will use SPRUCE
calculations to estimate a
tail temperature to be utilized in the
TORIC simulations.
Gary Taylor from PPPL visited last week to
work on CAMAC and
analysis software for the new ECE grating polychromator
(GPC2).