From:
IRBY@CMOD.PFC.MIT.EDU
Date: Wed, 27 May 1998 8:46:35 -0400
Reply-To:
IRBY@PSFC.MIT.EDU
Message-ID:
<980527084635.25a004f6@CMOD.PFC.MIT.EDU>
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT
Plasma Fusion Center
Alcator
C-Mod Weekly Highlights
May 25, 1998
Good progress on the TF refurbishment was
made last week. All
feltmetal has been removed from both the upper and
lower TF arms.
We are now removing the fiberglass layups from the outer
end of
the arms in preparation for cleanup and replating of those arm
surfaces
without feltmetal. The
between plate surfaces on both the upper and
lower core fingers have been
sealed. Sealing of the between turn
surfaces
on the upper core with a silicon rubber compound is nearly
complete.
As mentioned in previous reports, the core must be completely
sealed before
we can begin cleaning, electroplating, and electroforming
operations.
Work continues on inductive heating fixturing in preparation
for soldering
tests to be conducted later this week. Progress on both small area and full
area
feltmetal tests, and the diagnostics required for these tests has been
made. For the full scale test, a set of Rogowski
coils is being designed to
measure both total current through the
feltmetal pads and the current
distribution in the copper. In addition, thermocouple, voltage, and
optical
measurements are being planned.
A great deal of progress was make last week in tracking down
the
arc in FMIT#4. The problem has
been isolated to the EIMAC 2274 vacuum
tube. We replaced the this tube with a backup EIMAC 2274 and
produced
1 MW of power at 78 MHz before we developed an "arc" (forward
and
reflected power are equal) between the directional coupler looking
into the
FPA input cavity and its output cavity. We do not think this arc is
related to the previous one, and
this test therefore indicates that the
original fault was in the EIMAC
tube. Dr. Gerd Schilling from PPPL
visited
last week. We discussed
the PPPL antenna and some data from the last campaign.
The antenna is in
the assembly stage and electrical testing is not due to
begin for a couple
of weeks. We are currently expecting
the antenna to be
delivered the beginning of July. We intend to assemble the antenna
while
the machine is still on its assembly stand. This plan will relieve some of
the
pressure on invessel resources during machine reassembly.
We continue to proceed in the
implementation of a DNB for C-Mod.
Conditioning of the oil in the tank
shared by the arc/filament/snubber
supplies continued with steady
improvement of the breakdown voltage to
28kV. Detailed design changes and associated documentation for the
Master
Control Logic (MCL) chassis continued. The logic boards required in the
arc/fil/snub interface to
the MCL were ordered. Compensation of
the high
voltage dividers at the beam began. Modification to the MCL analog chassis
was begun. The kirk key relay interface chassis is now
designed, built,
installed and wired to the transfer block switches and to
the PLC
inputs and is awaiting testing.
The first version of VAX software for
control and timing of a DNB
conditioning shot via an IDL interface was
completed. Though it cannot as yet be used for hardware
control,
the program can detect C-Mod state and implements a means for
avoiding
collisions with C-Mod shots.
Work continued on the MCL and PLC interface
circuits and PLC
programming.
A review of
progress on DNB diagnostics and design of F-Port was held
on May 20 at
MIT. John Heard (Auburn) described the internal ECE optics. Ned
Eisner (U. Texas) discussed his
design for the beam limiting aperture required
for MSE and BES. Norton Bretz and Bob Parsells (both of PPPL)
traced recent
progress on design of MSE optics. Sanjay Gangadhara
described the side
periscope. Bill
Rowan (U. Texas) presented his design for the internal CXRS
optics and the
group design of F-Port flange.
Further
analysis has been done by Joe Snipes of fluctuations in H-mode
during the
980122 run in which plasma current and toroidal field were ramped
during
steady Enhanced D-alpha H-mode (EDA).
Although the fast (1 MHz and 2
MHz) sampled magnetic pick-up coil
signals were limited to 131 msec and 65 msec
duration, respectively, a
slowly sampled frequency comb filter array was used
to measure the
fluctuations in frequency bands from 56 kHz to 640 kHz. The
fluctuations in the range from 56
to 320 kHz all increased when ramping the
current down from 1.2 MA to 0.6
MA. At higher current, the fluctuation
levels
were considerably lower.
One detailed case of a magnetic precursor to an L-H
transition was
also analyzed in which a few oscillations were observed at
about 100 kHz
just before the transition. It appeared
to be high m and
n > 5 - 10 and was only visible on the outboard RF
limiter coils, suggesting
a high n ballooning character. The mode rotated in the electron
diamagnetic
drift direction. These
characteristics are similar to Type III ELM precursors.
Edge profiles measured by the new A-port
scanning Langmuir probe
during ohmic L-mode have been found to be similar
to profiles simultaneously
measured by the F-port scanning probe. These profiles constitute our
best
absolute density measurement in the edge and have been used by the
reflectometer
group to provide a calibration.
Miklos
Porkolab attended the NSTX Dedication Ceremony at PPPL, on
Monday, May
18th. He expressed the strong desire from MIT-PSFC to collaborate
on this
project. Bruce Lipschultz, Jim Terry,
Spencer Pitcher, and
Brian LaBombard attended the PSI conference in San Diego
last week.