From:
IRBY@CMOD.PFC.MIT.EDU
Date: Tue, 30 Jun 1998 9:05:32 -0400
Reply-To:
IRBY@PSFC.MIT.EDU
Message-ID:
<980630090532.25a0efae@CMOD.PFC.MIT.EDU>
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator C-Mod Weekly Highlights
June 29, 1998
Engineering:
Very good progress is being made on the TF
refurbishment. The
upper TF core
cleanup has been completed and the core is now ready for
plating and
electroforming. All TF arms, both upper
and lower, have
completed the cleanup process and are being inspected in
preparation for
plating. The
plating activity will be started early this week. Silver
plating samples have successfully completed cooldown
cycle tests to LN2
temperatures, and vacuum bakes and UT tests to reveal
any voids between
the copper and plating surface.
The inductive heating process has produced
very good temperature
distributions and full scale soldering tests have
begun. Careful
adjustments of the
inductive heating power and cycle time, and modifications
to the heat sink
were required to achieve these results.
We
have assumed in the past that measurement of the gap between
TF
fingers was an adequate measure of
feltmetal pad pressure. New
diagnostics
are being developed to directly measure this pressure
during machine
reassembly. In a related effort, we are
looking at better
designs and materials to be used in making the spring
plates that
apply the pressure to the pads.
We have continued to work on the control system for FMIT#3 and
#4.
We are waiting for parts to finish the repair job on #4's input
cavity.
One of the two EIMAC tubes which have been used in FMIT#4 has been
sent
back to the company for repair.
The tube holds DC voltage but breaks down
with application of RF
power.
We continued to make
progress toward the initial conditioning of the
DNB plasma source. The Arc/Filament/Snubber interface chassis
which links the
supplies with the master control logic and the PLC was
successfully tested.
Remote control and monitoring of the primary power
for the
Arc/Filament/Snubber supplies was tested. After correction of a problem in
the
monitoring instrumentation, and tests of the power and control phasing,
we
will begin pulsing the arc and filament supplies into the dummy loads.
The
dummy loads for the Arc/Filament/Snubber power supplies were installed
last
week.
Physics:
We
have experimental evidence of the formation of an internal
transport
barrier during off-axis D(H) minority heating.
The primary
evidence is a ~2.5-fold increase in neutron rate over
the H-mode only phase
with an associated 25% increase in central
density. Analysis of the x-ray
brightness
profile also indicates a central peaking (amplitude
increase by 50% and
the profile width decreases by 50%). In
addition,
the radiation profile suggests both a core and edge
barrier. As the
barrier forms, the
sawtooth amplitude decreases and the sawteeth are
eventually completely
stabilized. This behavior is
reminiscent of
PEP-mode, but without pellet injection. Preliminary analysis suggests the core
barrier
is formed following strong Elmy phases (the neutron rate increases
following
two Elm bursts and a dithering L-mode phase) and the radiated
power
profile also suggests a growing core barrier.
The mode is terminated
by MHD activity.
RF sheaths have been detected on magnetic
field lines connecting the
D-port RF antenna and the AB limiter. The RF voltage driving the sheaths is
deduced
from the decrement during RF to the floating potential measured by
a
Langmuir probe on an antenna side protection tile, and found to be of the
order
of 100V. Using the ion saturation
current density profile measured
by the A-port scanning probe, it is found
that on order of 1% of the net RF
power is lost to acceleration of ions
into the antenna and limiter by the RF
sheath voltage.
The 1998 Alcator C-Mod Ideas Forum is
being planned for August 19-20,
1998. The forum, to be held at MIT, will
consist of short (five minute)
presentations proposing experiments to be
carried out on Alcator C-Mod during
the next run campaign. Details
concerning the forum will be posted on the
C-Mod Web page
(www.pfc.mit.edu/cmod/) shortly, or can be obtained by
contacting Steve
Wolfe at wolfe@psfc.mit.edu.
Travel and Visits:
Dr. Gary Hallock from U. of Texas visited
last week to
discuss PCI (phase contrast interferometry) diagnostic
upgrades and the
fluctuation data collected thus far by Alex
Mazurenko. We agreed that
there
are two possible modes of operation for the system: heterodyne
RF mode and
plasma fluctuations mode. The former is
the primary
objective for the upcoming campaign because of its potential
in
providing long sought after core RF wave information. The fluctuation data
can be taken when
the diagnostic is not in use specifically for the
RF. Until we have a
fuller complement of diagnostics to help
determine where the fluctuations
are located, interpretation of the
results will be difficult. We will be adapting amplifiers built
for
the TEXT-U PCI system for the planned upgrade to 32 channels at
C-Mod.
We expect to have 12 amplifiers and spares ready by the fall for
the
upcoming campaign. Dr. Hallock
also provided some important insights
concerning the existing data and
established an initial direction for us
to proceed. This appears to be a very interesting
research development.
Gary
Taylor of PPPL visited to work on the 19 channel GPC2 instrument.
Modifications
to CAMAC modules were made and tested.
Progress was also made
on analysis of data from the last
campaign. Calibrated temperatures
and
radii are now available in the MDSPlus tree for selected shots.