From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
January
4, 1998
Engineering:
Work on Alcator C-Mod
last week focused on fixing the remaining small
vacuum leaks and
completing the new HEAT system. A base
pressure of
3 to 4 X 10-7 Torr has been obtained with one known leak
remaining on the Core
Thomson Scattering alignment target actuator. The RGA indicates that the major
component
making up the base pressure is water vapor (mass 18/ mass 28
~ 30), which
is coming primarily from the outgassing of invessel components.
The leak
has been fixed, we are pumping down, and we will soon do a final
leak
check before beginning to bake the machine.
The Heat system
is nearly ready for operation with 520 out of the
560 thermocouple channels
operational.
In addition to the
primary work mentioned above, we have continued work on the
new ECDC
waveguide run and Boronization and Gas systems. As soon as the
cooling jacket for the ECDC window has been
installed the new waveguide run
will be complete. The ECDC control system has been checked out
up to the point
of actually turning on the magnetron and checking forward
and reflected power.
We expect this final step to be taken early this
week. Only the water
sprinkler
remains to be hooked up on the Boronization system, and we will begin
a
Boronization system checkout using helium gas within the next few days.
The
Gas system is together and awaiting a leak check and bake before it is
ready
to be used. This system is required
before we can complete the
Core Thomson Scattering calibration that was
begun over the weekend.
We continue to bring both old and new
diagnostics back on line. The
Soft
X-ray and Magnetics systems are ready for operation. Improvements
to the TCI diagnostic are nearly complete, and
we expect to begin alignment
of the interferometer in the next few
days. A prototype Rangefinder
system
using single-mode fiber optics to relay both the 0th and 1st order
laser
beams to the machine is being tested. The rest of the ECE beamline was
installed in the cell,
optically aligned and pumped. Baking of the high
vacuum section is in
progress.
Work continued on modifications to the DNB Mod/Reg. This work included design
of some
control electronics and construction of enclosures to accommodate
the new
electronics. We continue to work on
grid drive, fault monitor,
tube regulator, and tube monitor printed
circuit board layouts and
fabrications.
Bus electronics
calibrations and checkouts were completed last week. A great
deal of data was taken for bus current and voltage
calibrations that is still
being analyzed. In addition, MOV Rogowskis, ground fault fuses and Pearson
transformers,
analogue links to the Hybrid, and bus current alarms have all
been checked
out and made operational. The Power
Systems Group has now begun
calibration and checkout of all the Alternator
electronics and CAMAC.