From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Organization:
MIT
Newsgroups: sci.physics.plasma
Alcator C-Mod Weekly
Highlights
January
18, 1999
Engineering:
Alcator C-Mod was
baked for several days last week as we prepared for
plasma operation. Following the bake, ECDC was started to
condition the
plasma facing surfaces.
This activity will continue for several
more days. The magnets have also been cooled down to
operating
temperature and successfully rung and hi-potted. The alternator has
been brought up to
full speed and testing of the power supplies into
the magnets has
begun. Many diagnostics are also being
debugged and brought
back online during this period.
Development
of the diagnostics and controls for the DNB continued. Matt
Sampsell, UT-FRC, visited PPPL to
test the fibers planned for MSE/BES on
C-Mod. A set of fibers was selected for shipment to MIT. Work on the
controls for the Mod/Reg
continued with electronics design and internal
cabling. Testing of the accelerator supply
electronics chassis boards was
completed.
The radiometer for
the ECE system to be supplied and operated by UT-FRC was
successfully
tested with the eight channels of the IF section. The
radiometer has been shipped for installation next
week.
We continue to install transmission line and coupling
components for the
new J-port antenna.
Vacuum conditioning of the D and E-port antennas
has begun.
An
existing one meter Ebert spectrograph has been modified to enable
dedicated
high resolution measurements of the Balmer alpha lines of
hydrogen and
deuterium, in order to monitor the time history of the atomic
D/H ratio at the
edge of all discharges. The spectrograph has been
outfitted with a 64 pixel
reticon photodiode array detector, and has been
calibrated using a lamp
containing a mixture of hydrogen and deuterium.
The measured instrumental
resolution is about .015 nanometers (half width
at 1/e). Light will be
collected using a fiber optic view at K horizontal,
with selectable polarizers
to discriminate between the pi and sigma Zeeman
components of the emission.
Absolute
calibration of the Michelson interferometer (ECE) system was carried
out
successfully on Tuesday. The
two-color-interferometer (TCI) is operational
and ready for plasma
operation.
The C-Mod Run Schedule on the Web has been updated.
Overall plans for the 1999
Campaign can be found at
http://www.pfc.mit.edu/cmod/run_schedule.html. Daily
operations
information can be found on the C-Mod Operations Calendar at
http://www.pfc.mit.edu/cgi/calendars/cmod,
which is updated sporadically as
information becomes available. Those
with access to the online OPS bulletin board
are advised to check there
for the most up-to-date schedule information.
The LOGBOOK was moved
from the legacy RDB database to a new Windows-NT
based database server
running SQLSERVER. This new database
is
considerably faster and more robust than its predecessor. The rest of
the databases will be
migrated after the dedicated database server
computer which has been
ordered is installed. When this is
completed we
will shut down our RDB databases permanently.
Physics:
Three
candidates are enrolled in the training course for new Alcator C-Mod
Physics
Operators that began this week. The course includes classroom sessions
and
practice exercises, to be followed by a brief apprenticeship during which
the
candidates will act as Assistant Physics Operators during the Startup
phase
of the upcoming run campaign. We expect training to be completed by the
start
of Physics Operation in February.
Travel and Visits:
Steve
Paul from PPPL visited last week to learn about
our setup for the AXUV
diode arrays (bolometric measurement)
on Alcator C-Mod. He is interested
in installing a similar
system for NSTX at PPPL. He met with Rejean
Boivin
to discuss details of our different arrays, including the
locations
and electronics. More
informal exchanges are planned in the near future.
Ricky Maqueda from LANL is at MIT this week working on his
IR periscope
and camera system.
Martin Greenwald travelled to
Washington D.C. to attend a meeting
of the ESnet steering committee
(ESSC). Issues discussed included
upgrades
to international connections; new requirements expected from the
SSI;
and possible new directions for the ESnet Coordinating Committee
(a
technical committee reporting to the ESSC.) Half a day was devoted to
relationships with the DOE program
offices. About 10 contract
monitors
representing most of the SC programs attended this session.