From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator C-Mod Weekly
Highlights
Feb 8,
1999
Operation:
The conditioning and facility commissioning
campaign continued at Alcator
C-Mod this week. Four run days were
scheduled and completed. The reliability
of the tokamak was excellent for
this phase of the run period, with startup
reliability of greater than 90%
during the last four days of operation.
The main tasks this week, aside
from cleanup and conditioning of the machine,
were diagnostic alignment
and calibration, conditioning of the D- and E-port
ICRF antennas, and
commissioning of the divertor bypass flappers.
On Tuesday a series
of reproducible 800kA diverted plasmas was run for the
purpose of aligning
the ECE view. The HIREX x-ray diagnostic also
used this run to
cross-calibrate its spectrometers, and the flappers were
exercised
successfully for the first time during plasma operation. In addition,
the
ICRF began conditioning activities, which continued as the main activity
on
Wednesday.
On Wednesday the RF power was increased up to 3 MW for
about 40 msec within a
few shots.
The performance then degraded and power was reduced. The system
resumed running cleanly at
lower power. New MW_coefficients and
DC2
and stub calibration factors for D and E-port were obtained. RF
conditioning
continued as a background task during the runs on Thursday
and Friday. By the
end of the week, the D- and E-antennas were operating
reliably at a total
power of 2.5MW.
Thursday's run was mainly
devoted to carrying out the first experiments with
the new divertor bypass
flappers, and related diagnostics. Three experiments
were conducted: an
ohmic density scan to look at the effect of the bypass on
neutral
pressures and Argon screening; a scan of strike point location at
fixed
density; and a transient 'puff and pump' experiment in which the
discharge
was initiated with the bypass open, and then the flaps were closed
at 1
sec into the shots. It was found that, for the same plasma density, the
main
chamber pressures are unaffected by the flapper. This is consistent with
earlier
conclusions that main chamber pressure is determined primarily by main
chamber
recycling and not by neutral escape from the divertor. Divertor
pressure is reduced by about a
factor of two with the flappers open, at all
densities. The Argon
penetration factor as defined by # Ar in plasma / # Ar
atoms released is
on average a factor of 2 higher with flapper open; this
difference is
smaller than expected from previous results. The transient
experiments are
still being analyzed.
On Friday, we began a two-day experiment
devoted to calibration of several
spectroscopic diagnostics. The sensitivity
of the McPherson spectrometer is
calibrated using the branching ratio
technique. This technique relies on
observation along the same
line-of-sight of two spectral lines
originating
from the same upper state, one in the VUV and one in
the visible. The
intensity ratio of such a pair of lines can be calculated
quite accurately.
Thus a calibration in the visible is to be transferred
to the VUV.
The line pairs used in Friday's run were:
D_0 1025
A (Ly_beta) & 6563 A (D_alpha)
D_0 972 A (Ly_gamma) & 4861 A
(D_beta)
He_0 537 A & 5016 A
He+ 247 A (Ly_gamma) & 4686 A
(Paschen_alpha)
He+ 256 A (Ly_beta) & 1640 A (Balmer_alpha)
Lines
also tried were CIV 312 A & 5801+5812 A.
The identification of the weak visible lines 5801, 5812
A
in the Chromex spectrum is questionable, but there appears to be
something
detectable. The McPherson calibration
is about 50% complete.
For HIREX the views, relative sensitivities,
and instrumental spectral
resolutions of each of five spectrometers was
calibrated. The calibration was
done by having pairs of spectrometers view
Ar lines from the same plasma region.
In addition the pairs' views are
scanned as much as possible so that
the entire poloidal cross-section can
be covered by the combination of all
five spectrometers. About 60% of this
calibration work was completed.
Engineering:
We
continued to work on installation of the DNB, new J-port antenna
feedlines
and transmitters, and a new vent system for the vacuum pumps in
the cell.
Over the weekend we backfilled the machine with hydrogen and
then argon to
complete the core Thomson Scattering calibration. Following the calibration,
we brought
the machine up-to-helium so that the new 2Pi bolometer could
be
installed.
Visits and
travel:
The C-Mod Program Advisory Committee met at the PSFC on Feb.
4-5. The PAC
members attending, D. Hill, E. Synakowski, E. Strait, B.
Carreras,
C. Gormezano, and P. Efthimion, heard presentations on the
status of the
C-Mod facility, near-term program, and long-range plans. Our
OFES contract
monitor, R. Dagazian, also attended the PAC meeting. R.
Hawryluk and
N. Sauthoff from PPPL participated in the discussions on the
first day.
Gary Taylor (PPPL) is now at C-Mod working on the ECE
system.
Stewart Zweben (PPPL) visited the PSFC this week, and
presented an idea for a
2D turbulence imaging diagnostic, which could be
implemented on C-Mod in the
next run campaign.
During the week
of Feb. 1-5, 1999, Dr. Shunsuke Ide visited the
Alcator C-Mod Group at the
PSFC. He worked with Paul Bonoli on
a JAERI / MIT collaboration related to
implementing an improved
version of the ACCOME Lower Hybrid (LH) Module at
JAERI. The code
was run through numerous physics checks after installation
on
a UNIX workstation at JAERI. Several test cases were run for the
JT60/U
LH current drive experiments, including experiments where
a reverse shear
configuration was sustained by LH current drive.