From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
Feb
16, 1999
Plasma Operations devoted to machine clean-up and facility commissioning
continued
on Alcator C-Mod last week. Four run days were scheduled and
completed. Startup reliability of C-Mod has been almost
95% over the last two
weeks of operation.
Tuesday's run
completed calibrations of the VUV and x-ray spectrometers.
Reproducible,
"constant" with auxilliary gas puffs of Ar and He were required
and
achieved. The views, relative sensitivities, and instrumental spectral
resolutions
of each of five x-ray spectrometers was calibrated. This was done
by
having pairs of spectrometers view Ar lines from the same plasma region.
In
addition the pairs' views were scanned so that the entire
poloidal
cross-section is covered by the combination of all five
spectrometers. For the
VUV spectrometer the sensitivity was calibrated
using the so-called branching
ratio technique. This relies on observation
along the same line-of-sight of
two spectral lines originating from the
same upper state, one in the VUV and
one in the visible. The measurement
of the visible line is made by an
instrument whose sensitivity has been
calibrated by other means. In this way
the calibration in the visible is
transferred to the VUV.
Wednesday's run was dedicated to calibration
and testing of the fast-scanning
gas-injection probe. Controlled amounts
of ethylene and freon gas were first
puffed into the vacuum chamber to
correlate quantity injected with plenum fill
pressures and optimize valve
timing. Plasma experiments were
performed in
which freon was injected into 0.8MA discharges with
line-averaged density
around 1.5e20 m-3.
The amount of gas injected and the insertion depth of the
scanning
probe were varied. Measurements of fluorine were made with the
McPherson
and measurements of chlorine were made with HIREX.
High power
conditioning and testing continued on D and E-port antennas on
Thursday
and Friday. Up to 3MW total power was
launched into the
plasma. Although the H/D ratio continued to be higher
than optimum, some
heating was observed. On Friday several L-H transitions
were obtained.
Reliable operation has been achieved with E-port antenna
and its ICRF system.
D-port, however, continues to be inconsistent. The symptom is variable power
for the
same input voltage. The problem seems
to be in the low power
amplifier chain, not in the IPA, Driver, or FPA stages. All but the signal
generator were
swapped. The symptom disappeared when a
splitter was installed
between the signal generator and the mixer. The signal generator, however,
did not
show a drift in the RF output or any other problems when tested on the
bench.
We will continue to monitor this inconsistency.
Progress on tuning
FMIT#4 to 78 MHz goes slowly. The
maximum
frequency at which the RF output is 2 MW is 75.6 MHz. At this point
the driver reaches its
minimum length and can be adjusted no
further. As the frequency is increased further, the reflected power
from
the FPA input cavity increases and the output power decreases so
that at
78 MHz only 700 kW is produced. Chris
Brunkhorse (PPPL RF engineer)
is visiting on Tuesday of this week to help
troubleshoot the problem.
The first boronization of the machine
during this run campaign was carried out
last Friday evening, extending
into Saturday morning. After
approximately 200
plasma discharges the machine was judged to be
sufficiently clean to boronize.
Assuming uniform deposition, approximately
1900 Angstroms of boron was applied
to the vessel walls using ECDC with a
fill pressure of 3 to 5 mTorr of B2D6
(diborane). Following boronization, we have run ECDC in
helium to deplete
somewhat the deuterium on the walls.
A
schedule for bring up the DNB has been prepared and reviewed. Principal
milestone
dates are:
Operation of DNB on
test stand complete - 5/19/99
DNB
tests into CMOD plasma complete - 8/2/99
Present progress measured against
this schedule is satisfactory.
Arrangements are being made to obtain
supplemental engineering support from
UT during the final system testing
phases immediately prior to the above
milestone dates.
Visits
and Travel
------------------
Dave Johnson (PPPL) visited last Sunday
and Monday to help with alignment of
the edge TS system.
Ron
Parker, Dave Gwinn, and Steve Wukitch visited PPPL to meet with
Stefano
Bernabei, Neville Greennough, and Elmer Fred to discuss,
survey, and
assess the MIT lower hybrid equipment at PPPL and the
proposed LH
experiment on C-mod.