From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Organization: MIT
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Highlights
Mar
22, 1999
The scheduled maintenance period on Alcator C-Mod continued
last week. No
plasma operation was scheduled. A short, clean vent with He
backfill was
carried out on Friday, in order to install a detector array
designed to
measure deuterium Lyman alpha emission with high spatial
resolution. A visual
inspection of in-vessel components including limiters
and ICRF antennas was
carried out using a borescope; all inspected
components were found to be in
nominal condition. The vent was completed
before noon, and the machine pumped
down again. Electron cyclotron
discharge cleaining was run over the
weekend. The maintenance period will
continue this week.
The omegatron probe, which combines a gridded
energy analyzer and an
ion mass spectrometer, was sucessfully aligned with
the toroidal
magnetic field. A
fixture was added to permit a few degrees of
rotational freedom from a
linear motion bellows. The alignment
was
checked by inserting the omegatron into an ECR plasma and
measuring
the electron current to the ion collection plates.
The Experimental Program
Committee met on Monday to review miniproposals for
the next operational
period. Nine new or revised MP's were approved.
ICRF Systems:
-------------
The
J-port 78 MHz coax configuration was installed, and the system is now
ready
for testing. A fixed decoupling stub, which will replace the
presently-installed
tunable stub, is being manufactured along with components
for the 60 MHz
configuration. FMIT#3 was tuned to 78
MHz and produced 2+ MW
for short pulses before the transmitter
failed. The problem was
associated
with a mechanical malfunction that resulted in an arc the FPA
output cavity.
One of the drives for the tuning element was slipping. Over time, this
resulted in a
misalignment of the tuning element. The
tuning element was
replaced by a spare and the drive mechanism was
adjusted to avoid this problem
in the future. Chris Brunkhorst (PPPL) has also investigated the placement
and
length of an additional stub to lower the plate impedance, which would
lower
the necessary voltage to produce 2 MW.
The critical path item is
FMIT#3.
Once the present problems have been fixed, system testing can
begin.
The D-port stub tuner was repaired and installed last
week. Initial tests (10
kV high
pot and verified range of motion) indicated that the repair was
successful. The more demanding power tests will be done
once the system is
evacuated and back-filled with N2.
Diagnostic
Neutral Beam:
------------------------
Testing of High Voltage
Crowbar was completed. The high voltage system is now
ready for
installation and testing of the modulator/regulator circuits. As
was reported last week, we are
somewhat behind schedule because of a delay in
the design of the tube
reg/monitor PC board, due to a software problem. This
task has now been
completed. All other progress continues to be satisfactory.
Visits
and Travel:
------------------
Drs. Noriyuki Inoue and
Hisamichi Funaba from LHD/NIFS visited C-Mod on Mar 15
and 16, to review
our surface analysis of Mo tiles and dust from the vacuum
chamber, and to
look over the laser blow-off system. The LHD and C-Mod glow
discharge and
ECR vessel cleaning techniques were also discussed.
Romik
Chatterjee of UT-FRC began a 1 month visit to C-Mod to work on
hardware
and data analysis for the FRC/AU ECE heterodyne radiometer.
Ashley
Shugart, a UT-FRC graduate student and his thesis advisor, Gary
Hallock,
arrived to kick off Ashley's first extended visit to C-Mod. While
here, Gary worked with Ashley and
Alex Mazurenko (PSFC) to remove
oscillation problems in the PCI amplifiers
supplied by UT-FRC for interim
use while new amps are being designed and
constructed at UT-FRC. Bill
Rowan,
UT-FRC, returned to UT during the week to package and ship fibers
and
fiber optic hardware for the CXRS tests.
Raffi Nazikian (PPPL)
visited last week to work on the reflectometry
diagnostic on C-Mod with
Yijun Lin and Jim Irby. During his visit, he helped
identify the source of
a phase error which had been previously noted in
reflectometer profile
data. The problem appears to have been magnetic field
effects in a ferritic
component; local shielding to remedy this problem is
being
implemented. Raffi plans to continue to
help with hardware upgrades to
the C-Mod system, bench marking of the PPPL
and MIT 2D codes, and data
analysis.