From: WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly HIghlights
                  Apr 5, 1999

Alcator C-Mod resumed plasma operations last week. Three runs were scheduled,
but only one was completed. The scheduled runs were primarily dedicated to
check-out and conditioing of the ICRF systems. During the run on Wednesday, it
was determined that an arc had occurred in the E-port transmission line, as
described below, and the Thursday and Friday runs were cancelled so that the
line could be repaired.

Aside from this arcing problem, the run on Wednesday was successful and
productive. This was the first day of plasma operations following several
weeks of maintenance activities, during which a "clean" vent of the vacuum
system was performed. The machine condition was good. Startup reproducibility
was high, and impurity levels, including Mo, were low.  EDA H-modes were
readily obtained at about 1MW of RF power. The RF power was brought up to
1.7MW, mostly from the D-port antenna.

Several piggyback experiments were carried out. The FSP fast scanning probe
was observed on the video system, in preparation for plume imaging
experiments. Ron Bravenec (U. Tx) completed installation and first operation
of the BES system by observing continuum emission to the red of D-alpha.  All
eight channels produced signal with low noise.  Edge-peaked fluctuations were
observed above 50 kHz. Data was obtained on the Omegatron edge plasma
diagnostic, which had been aligned during the maintenance period. This probe
combines a gridded energy analyzer and an ion mass spectrometer. Analysis of
these data is proceeding.

Physics & Analysis:
-------------------

First results from the new Kaiser spectrometer have been obtained.  The Kaiser
system consists of 14 spatial chords looking tangentially at the plasma
boundary (spatial resolution ~ 3 mm).  In addition to observing Halpha and B
II profiles, the spectrometer views three He I lines emanating from a helium
gas jet which is fixed to the side of the AB split limiter.  Using the ratio
of the three He lines, it is possible to derive the local ne and Te profiles.
This work is in collaboration with PPPL (which has loaned the spectrometer)
and TEXTOR (which has supplied the theoretical line ratios).

First ne and Te profiles are very encouraging.  Full profiles from several
centimeters outside the separatrix to approx 1 cm inside have been obtained.
There is reasonable quantitative agreement with the ASP (probe at
approximately the same location), particularly with respect to the density
profile.

We will continue to obtain data with the new system and hope to provide some
scalings for separatrix values of ne, Te and their gradients.

ICRF Systems:
-------------

Initial testing into plasma indicated an arc in the E-port transmission line
between the transmitter and stub tuner that prevented increasing the power
beyond ~400 kW.  The initial damage was probably done during testing with an
improper switch set ting.  Upon disassembly, an elbow assembly was found to
have arced.  The elbows were replaced with spare elbows and tested under
matched and unmatched vacuum conditions.  To avoid a repeat of this problem, a
proceedure will be put in place requiring visual inspection of switch
positions. A lockout and monitoring system will also be implemented.  On
FMIT#1 and #2, the FPA screen current limit was changed from 4 A to 7.2 A
(recommended screen current limit).  This change should eliminate some screen
overcurrent crowbars that occurred during the last campaign.  With the help of
Chris Brunkhorst and Gary D'Amico (PPPL), a general survey of FMIT#1 and #2
were conducted to establish documentation of present system and to identify
systems that limit output power.

The J-port 9" coax has been reassembled, including the phase shifter
#3.  The phase shifter required reconditioning of the push/pull rod
connection.  The system was evacuated and is currently pressurized to
5 psi N2 (15 psi will be the initial operating value).  All the Mega
coax elbows have been inspected and those that failed were modified.
Vacuum tuning and testing will begin shortly.

Travel and Visits
------------------

Gary Taylor returned from PPPL to work on the 19-channel grating
polychromator.  He modified the filters on the fast channels, which gave
improved signal to noise.  During the maintenance break, he completed
analysis of electron power deposition in some previous RF modulation
experiments, which showed good agreement with TORIC and other RF codes.

Tom Fredian has returned from his trip to the Australia National University in
Canberra, Australia, March 8-19 to install MDSplus for use on the H-1 Heliac
experiment.