From: WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT              


                  Alcator C-Mod Weekly Highlights
                        May 10, 1999

Last week was a maintenance week at Alcator C-Mod. No plasma operations were
scheduled. This week will also be a maintenance week.

Physics and Analysis:
---------------------

The high resolution (0.7 mm at plasma edge) toroidal Z-Meter array, which
images free-free bremsstrahlung emission from the plasma, has been used to look
at EDA H-mode discharges. A clear pedestal in the emission forms, with tanh
fits giving the pedestal foot location at or near to ( within about 2 mm) the
outboard midplane location of the last closed flux surface derived from EFIT
reconstructions. Typical emissivity full-widths range from 4 to 6 mm.

Analysis of the rangefinder data indicates a linear trend in differential
motion of the inner wall with halo current.  We have measured up to 47 um of
movement with a halo current of 170 kA.  These results are being incorporated
into the simulations needed to guide the design of the inner divertor upgrade.


ICRF Systems:
-------------

As a result the tube failure in FMIT#2 and another suspected failure in FMIT#1
(tests are still ongoing), a review was conducted to investigate whether the
tubes are adequately protected and whether our operating practices were a
contributing factor in the loss of these two tubes.  This review was
undertaken in collaboration with PPPL (Chris Brunkhorst, Joel Hosea, Gerd
Schilling, and Randy Wilson).  As a result of this review, several
modifications and additions to the protective circuitry are being undertaken,
including installation of an additional "soft-start" resistor, a screen
crowbar circuit, and a low-stored energy grid bias regulator circuit. In
addition, a circuit was installed to disable the rf drive during a
crowbar. These modifications are being made to all four transmitters. We plan
to have FMIT#3 and #4, which are connected to the new J-port antenna, prepared
for testing early this week with the aim of beginning operation into plasma
next week.  FMIT#1 has had an 8973 tube installed (should provide ~ 1 MW) and
FMIT#2 has had a reconditioned 2274 tube installed (should provide ~2
MW). Both of these units will also operate once all of the above modifications
have been made to them.

In addition to the ICRF engineering issues, Joel Hosea and Randy Wilson
visited to discuss the ICRF priorities for the remainder of the current
campaign.

Diagnostic Neutral Beam
------------------------

During the past week it was necessary to divert technical and engineering
resources from the DNB to the ICRF transmitter modifications. This resulted
in a schedule slip of nearly one week for the completion of the DNB. We
still anticipate that the DNB will be ready for testing at the commencement
of the scheduled outage this summer and that the installation onto the
tokamak and final comissioning of the beam will be completed in time for
the beginning of the FY 2000 operating campaign.


Travel and Vistors
-------------------

Marco Brambilla has been visiting the PSFC and working with the Alcator C-Mod
group since April 19, 1999.  His visit will continue until May 14, 1999. He
has been working mostly with Paul Bonoli on the implementation of a new
version of the toroidal ICRF code TORIC on our local workstation cluster. The
improved TORIC module now computes the electron damping of ion Bernstein waves
using a new formulation which relies far less on a numerical broadening (ad
hoc) of the ion-ion hybird layer as did the previous version. The code has
also been coupled to an ICRF current drive module that was developed at
MIT. The new code is being tested and compared with the old code as as well
as with experimental data from mode conversion electron heating in C-Mod.
Some effort has also been devoted to the implementation of an IDL
post-processor for TORIC that can be used both at Garching and MIT. This will
facilitate the transfer of future versions of the ICRF code between MIT and
the US under the ASDEX Upgrade - US collaboration agreement.

Perry Phillips (U. Texas) will be at M.I.T. for the rest of this month to work
on the high resolution ECE system.