From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
July
26, 1999
Plasma operations continued at Alcator C-Mod last week. Three
runs were
scheduled and completed. All the runs were devoted to
commissioning of the
ICRF system and conditioning of the antennas.
The
shot duty cycle continued to be limited by cooling of the alternator, due
to
the relatively high temperature (73F) of the river water at the inlet of
the
heat exchanger. Maintenance on the heat exchanger was performed this
weekend,
and it is expected that this unit will operate more efficiently in
the
next series of runs. Startup reliability was unexpectedly low during the
Wednesday
and Thursday runs; it was subsequently discovered that the
pre-ionization
source was not operating. This was remedied on Friday and
startup became
significantly more dependable.
Physics and Analysis
--------------------
First
data from RFPCI (RF phase contrast interferometry) was obtained. The
RFPCI measures the density
fluctuation associated with the launched RF wave.
This diagnostic will
allow measurement of core RF waves. Probes will continue
to provide
information about the edge. Initial
analysis suggests that the
amplitude scaled with injected RF power. Further testing and experiments is
required
to verify operational and measurement reliability.
ICRF System
-----------
Good
progress was made in conditioning D and E-port antennas. Both FMIT#1 and
#2 worked up to their
operational limits. FMIT#1 is limited
to between 600 -
800 kW because of its 1 MW plate dissipation
limitation. FMIT#2 is limited to
about
1.4 MW by the high voltage supply, which is currently being operated at
the
lowest transformer tap position. The
anode voltage will be raised on all
the transmitters as the intial
commissioning is completed. We were able to
inject up to 1.4 MW into the
plasma; however, on some discharges the
transmitter overloaded at the
L->H transition. More reliable
operation was
achieved at 1.2 MW.
Until the anode voltage can be raised, the reliable power
will be
limited to this power level.
The
first significant power from J-port was obtained as well. Power ramps up
to 600 kW were obtained
from FMIT#3 and up to 150 kW from FMIT#4.
More
conditioning effort is required to increase the output power
and run them
simultaneously.
The repair of the FMIT#3 phase
shifter was completed. The FMIT #4
phase
shifter has a G11 push/pull rod like the one in PS#3, and this will
probably
need to be replaced in the near future. We plan to continue to
run FMIT#4 at
moderate power levels since a great deal of information
about J-port antenna
operation can be obtained. The phase shifter will be upgraded as soon as a
several day
long window can be scheduled.
Components for the upgrade are
being fabricated.
A
long-standing problem associated with FMIT#1 breaker was solved. There were
intermittant breaker
closings as a result of the relay coil being
marginally driven. Removing a stepdown transformer between the
240V supply
and the relay allowed the breaker to function properly.
Diagnostic
Neutral Beam Systems
-------------------------------
Finite
Element Analysis calculations are being performed on the neutral beam
superstructure
from the wall to the tokamak. Results will determine the size
and cross
section of the beams to be used to carry the load.
Data
Acquisition
----------------
Compaq Corporation and Jorway
Systems have been investigating an intermittent
problem we have been
experiencing with our CAMAC serial highway equipment. The
problem causes
SCSI bus time-outs which often results in the loss of data from
one or
more CAMAC modules. During the course of a normal run day we might
experience
two or three of these time-outs. Last week Compaq provided us with
a
patched SCSI software driver for OpenVMS. Since the new driver was
installed
we have not experienced any more of these time-outs.
Travel
and Visitors
--------------------
Many C-Mod physicists
participated in the 1999 Fusion Summer Study,
"Opportunities and
Directions in Fusion Energy Science for the Next Decade"
held at
Snowmass, CO, over the last two weeks.
Josh Stillerman attended the
2nd IAEA Technical Committee Meeting on Control,
Data Acquisition and
Remote Participation on Fusion Research which was held in
Lisbon,
Portugal. Josh gave an oral presentation titled "WWW interfaces for
runtime
relational database applications".