From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Organization: MIT
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
August
16, 1999
Plasma operations continued at Alcator C-Mod last week. The
principal focus
continued to be commissioning of the RF systems. Plasma
runs were carried out
on Wednesday and Friday. Standard 1MA, 5.4T single
null plasmas were run to provide
targets for the RF. The runs scheduled
for Tuesday and Thursday were cancelled
to facilitate work on the RF
system.
Physics & Analysis
------------------
An
IDL routine has been written which automatically determines the
confinement
mode (L-mode or H-mode) of the plasma by looking at the edge
soft x-ray
brightness profile from the outboard midplane. The routine
takes advantage of
the fact that the soft x-ray emissivity develops a
pedestal shape in H-mode,
and that the emissivity at the top of this
pedestal typically is 10-40 times
higher than the emissivity in L-mode.
Initial testing indicates that the
routine is very reliable, but not
fool-proof. The routine may become
a
valuable tool for statistical analysis of large amounts of plasma data
where
manual determination of the confinement mode is not feasible.
ICRF
System
------------
Last Monday, 8/9, we noted a large pressure
excursion on the FMIT#3 2242 final
amplifier tube. Though the pressure came down, it never
recovered to an
operational level.
We continued to monitor the tube on Tuesday while work
continued on
the RF power feedback systems mentioned in the last weekly
report. We operated C-Mod on Wednesday and
successfully tested the feedback
system on the J-port antenna using
FMIT#4. Having completed this test,
we
stopped the run and did a high-pot of the 2242 tube. When the tube failed the
hi-pot test,
we disassembled the cavity and removed the tube. We found that
one of the water cooled filament connections
to the tube was badly discolored.
It is clear that this filament
connection was not being cooled adequately, and
that the resulting
overheating caused a leak. This
incident is still being
investigated, and a report will be issued at a
later date. The 8 to 9 year
old
tube was installed at MIT in 1996. It operated successfully during our 40
MHz
campaign in 1997, and during the many hours of operation needed to bring
up
the new J-port antenna. All filament
cooling lines on the other three
transmitters have been checked and found
to be properly cooled.
We have now installed the 2274 2.5 MW tube
from FMIT#2 into the FMIT#3 cavity.
The flow of cooling water to the tube
has been verified and all associated
alarms and interlocks have been
tested. FMIT#3, with the 2274 was
tested at
low power during the run on Friday. This change will ultimately give us 4 MW
of RF power
capability into the J-port antenna.
We are working with GA to obtain
another 2274 tube for the FMIT#2
transmitter. We hope to have this 2274 in
house by midweek, with installation
and testing typically taking about one
full week.
Travel and Visitors
--------------------
Dr.
Ricky Maqueda from LANL is on site for a week to investigate edge
fluctuations
and "filaments" as seen by gated (~10 microsec), fast framing
(1000
fps) camera. He will also be running the IR camera system. This is part
of the C-Mod collaboration
with LANL.