From: WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Organization: sci.physics.plasma
Newsgroups: plasma@cs.uml.edu
Organization: MIT


                  Alcator C-Mod Weekly Highlights
                        August 23, 1999

Plasma operations continued on Alcator C-Mod last week. Five run days were
scheduled. The run on Thursday was terminated after one plasma shot due to
malfunction of a 13.8kV breaker; this was repaired and normal operation
resumed on Friday morning. The machine operated well, with 72 plasma shots
produced with typical currents of 1MA and toroidal fields of 5.1 to 5.4T. The
main focus of operations continued to be commissioning of the J-port ICRF
antenna. In addition, a series of ohmic H-mode shots were run in support of
several experiments, including Edge Fluctuation imaging, Puffing probe plumes,
and Omegatron; on these shots, the RF was pulsed at the end of the current
flattop.

Physics and Analysis
--------------------

On Wednesday's run, the F-port and A-port scanning Mach probes were configured
to record cross-field profiles of floating potential and ion saturation
current fluctuations during L and H-mode phases of ohmic H-mode discharges. In
previous attempts to monitor ion saturation currents with these probes, the
Isat probes were held at a constant bias.  This caused a runaway heating and
arcing condition. For this run, a voltage sweep was maintained on the "Isat"
probes. During data analysis, the Isat portion of the sweep will be extracted
for fluctuation analysis.  Preliminary results suggest that the 6 mm poloidal
spacing between the "north" and "south" probes is too large to reliably record
poloidal E-field fluctuations. This is necessary to allow an estimate of the
local cross-field fluctuation-induced fluxes. However, good correlation is
seen in floating potential fluctuations between the "North" and "East (or
"West") probes which have a 3 mm poloidal separation. A redesign of the high
power-handling Mach probe head with closer probe spacing is being considered.
Such a design would allow both fluctuation-induced particle fluxes and
parallel plasma flows to be recorded up to the separatrix.

The Beam Emission Spectroscopy receiver was used to look at fluctuations in
D-alpha emission. The views were essentially toroidal.  We hoped to see
correlations and phase shifts between poloidally separated views, with the
goal of determining the radial electric field.  Instead, we saw highly
correlated fluctuations (for frequencies below ~50 kHz) between *radially*
separated views across almost the entire plasma.  In contrast, poloidal
correlations rapidly dropped off with separation of the views.  In both cases
there was little (poloidal) or no (radial) indication of propagation.

We interpret these results as due to contamination by D-alpha emission from
the near- and far-fields of the views.  We will next try a couple of
modifications of the system:
      i) reduction of the collection angle of the optical system to
minimize D-alpha collected in the near and far field (by stopping down the
light cone exiting the optical fibers),
      ii) detection of bremsstrahlung emission, which peaks closer to the
foci of the views.


ICRF System
------------

We continued J-port antenna conditioning and testing into 5.2 T plasmas (H
resonance is on-axis at 78 MHz), and were successful in demonstrating heating
with the J-port antenna.  Scanning different relative antenna strap current
phases, the best heating was observed with [0,pi,pi,0].  Other phases did not
result in H-mode and had signficantly more impurity influx, particularly Ti,
Mo, and C.  The H/D ratio was increasing with RF power and throughout the day.
The hydrogen source may be the TiCN coated Faraday screen.  We found that full
current disruptions could be avoided by lowering the RF power.  A small
density scan suggested that the impurity injections were insensitive to
density.  With an outer gap of 8-10mm the antenna loading was high (above 10
Ohms). The antenna operated with lower loading (more like normal D and E-port
loading values) with an outer gap at 1.2 cm. Operation this week will
determine if more conditioning of the antenna can reduce the impurity source.

In FMIT#3 and #4, the low power RF amplifiers and control system have been
further investigated.  An upgrade to power feedback circuit has been
implemented and tested into dummy load, vacuum, and plasma.  It functions
better than its predecessor and will undergo further refinement.  Although the
reason is unclear, a 56 kHz amplitude modulation in the 78 MHz signal was
found to be related to the presence of a splitter between the preamp (10 W)
and the Kalmus amplifier (<500 W).  A new set of splitters was installed and
the amplitude modulation was eliminated.

The Eimac 2274 tube from GA arrived, and, following inspection (including
photographs), cleanup, and hi-potting, was installed in the FMIT#2
transmitter.  FMIT# 2 will be tuned and tested into dummy load at power levels
up to 2 MW.  The cavity high voltage connection was upgraded as well, and was
high potted to 30 kV in situ.  We anticipate operation with this tube into
plasma (E-port antenna) this week.


Travel and Visitors
--------------------

Miklos Porkolab attended the FESAC Panel meeting in Knoxville, Tenn, from
Aug. 18 through Aug. 21.

Ron Bravenec (U. Texas) was at C-Mod last week looking at D-alpha fluctuations
with the BES system optics.

Perry Phillips continued his stay working on the UT ECE system.  Software
was developed to look for changes in local Te gradients, the slow ECE
channels were reconfigured to improve signals, and a new temperature
fluctuation IF system was added.