From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator C-Mod Weekly Highlights
October 18, 1999
The
C-Mod maintenance period continued last week and preparations for machine
operation
scheduled to begin this week were made.
Cooldown of the machine
was begun on Wednesday, 10/13. By Friday, the TF magnet was cool enough
for
some low current resistance tests to be made. These tests indicated that
warming up
the machine had succeeded in reducing the TF resistances back to
nominal
levels.
C-Mod operation resumed on Monday, 10/18, with successful
tests of the TF magnet
followed by an RF conditioning run. Three out of our four transmitters ran
during
the last half of the run. FMIT#2 was
not operated because of a fault
indicator problem discussed in detail
later in this report. Startup
reliability
was 100%.
Physics
-------
The previously observed
coherent high frequency magnetic fluctuations around
600 kHz in Enhanced D
alpha H-mode (EDA) have now been observed again with
both D and E port
antennas running, and the hydrogen concentration was
5% or less. There appears to be a threshold of between 1
and 1.5 MW of RF
power to drive these modes. They persist throughout the EDA phase and continue
after the
RF is switched off for typically 10 - 15 ms.
These modes have
also been observed on the Phase Contrast Imaging
(PCI) diagnostic at about 400
kHz because of aliasing about the 1 MHz
sampling frequency. The time
history
and changes in frequency of the mode are clearly correlated with
the fast
magnetic fluctuations.
The 1 MHz magnetic fluctuations are aliased in the same
way, but
the 2 MHz magnetic fluctuation data shows clearly the true frequency
of
the mode. In some discharges the signal
was strong enough on the PCI to
determine the major radial k number of the
mode, and it was found to have
k_R = 2 cm^-1, which is near the limit of
spatial resolution of the fast
magnetic pick-up coils. Because of the line integrated nature of the
PCI
measurement, it is not possible to determine the radial location of
the mode.
Engineering
-----------
FMIT#1 and #2 were
each successfully tested into a dummy load at the 2.5 MW
level. The output power was limited by the screen
current rollback and the
anode current overload on FMIT#1 and #2,
respectively. The RF
instrumentation
(Kalmus, IPA, and driver forward and reflected power) has
been upgraded,
installed, and calibrated. Fault
protection circuits were
tested in both system and component level
tests. These tests
are now part of
a routine maintenance program. A fault
indicator in
FMIT#2 was found not to be resetting properly. The consequence was that the
system
would turn off upon a fault, but the operator would not have a
record of
which fault caused the RF to shut down.
The problem was
identified as a low reset signal level caused by a
overloaded line driver.
This circuit is now being repaired.
The
phase feedback units have been installed in FMIT#3 and FMIT#4 and
reconfiguration
of the low power RF chain in these units has been completed.
Testing of
the phase feedback system during operation into vacuum has begun.
The phase feedback system will
maintain a set phase shift between the two
j-port transmission lines.
We
have completed a version of the resonant loop configuration
capable of
[0,pi,0,pi] and [0,pi,pi,0] phasing of the j-port antenna using a
variable
length stub. The measured resonant
frequenies of the loops are 77.9
MHz and 78.11 MHz. The decoupling stub electrical length is 6.1
cm, and the
decoupler isolation is -50 dB. The variable length stub will eventually be
replaced with a
fixed length stub once the proper stub length is determined.
Work
progressed on the DNB last week. The
design of the HV/Mod-Reg interface
has been completed and work has started
on modifying and stuffing the
PC boards.
Detailed wiring diagrams for the HV/Mod-Reg interface chassis has
been
started. Installation of the low
capacitance duct has continued, and
high voltage cables have been
terminated at the diagnostic lab.
The
Arc/fil/snub duct and cabling have been installed in the
cell. Final
alignment of the duct
and attachment to supports is underway.
HV
cables in the cell transition box have been terminated.
C-Mod
Quarterly Review
----------------------
On Wednesday, 10/13, a
C-Mod DOE Quarterly Review was held via video
conference. Both MIT and U. Texas made
presentations. MIT reported on
C-Mod
engineering activities and new physics results, with emphasis on
data from
the new high spatial resolution edge diagnostics. U. Texas reported on
data obtained
during the current campaign from instrumentation that will
eventually be
used in conjunction with the DNB operation.
Reporting MIT work
were Rejean Boivin, Martin Greenwald, Bob
Granetz, Ian Hutchinson,
Jim Irby, Yijun Lin, Bruce Lipschultz, and Steve
Wolfe. Bill Rowan discussed
the U. Texas results. Rostom Dagazian, Ray Schwartz, Chuck
Finfgeld,
John Willis, and Warren Martin represented OFES.