From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: MIT
Alcator C-Mod Weekly
Highlights
January
10, 2000
We continued focusing work last week on the
DNB, RF, and invessel work
including the re-installation of the RF
antennas. Work also progressed
on
maintenance of C-Mod power systems.
Engineering:
All
work was completed last week on the OH commutation switches. This work
primarily involved cleaning
high voltage switches, checking high voltage
connections, improving some
of the high voltage insulation, and generally
cleaning up in and around
all the racks. General maintenance also
continued
on the power supply breakers.
Each breaker has been checked mechanically
according to the GE
service procedures, hi-potted, and generally cleaned
up. Similar maintenance has also been completed
on the TMX contactors.
All high current bus connections on the TMX
supplies have also been
throughly checked out. Finally, another TMX supply is being brought on line
as a
backup supply for the alternator exciter.
Invessel work included
re-installation of the D and E antennas.
The D-port
antenna will be declared installed as soon as the final
torque check is
complete. Boron nitride
tiles for the E-port antenna are being fit up invessel
after which they
will have to be baked. A fitup of the
J-port antenna outside
the vessel is nearly complete. Les Gereg and Joe Frangipani came up
from
PPPL to direct this effort.
Invessel installation of this antenna will begin
this week. Other invessel work included repair to the
H-port flux loop
mentioned last week.
Inner divertor modules have been removed from the
machine and are
being machined to provide new views for inner wall
retro-reflectors. Work also continued on a new mirror mount to
be installed
at A-Hor. This mirror
will allow a much better TV view of the J-port antenna.
Work on the
DNB included continued operation of the MOD/REG supply, and
commissioning
of the engineering components of the CAMAC data acquisition
system. On Friday, the beam supplies were operated
into the beamline for
the first time.
Physics:
Last
Thursday a final design review of the new 2-D imaging bundle was held
via
a video conference involving PPPL, MIT, and LANL. This new diagnostic
will view the edge plasma with
sufficient temporal and spatial resolution
to study edge
fluctuations. Reviewers from PPPL
included Gerd
Schilling, Dan Simon, Larry Dudek, Bob Parcell, Steve
Raftopolous, Dave
Johnson, and Stewart Zweben who was at MIT and is
leading this effort.
Jim Terry, Earl Marmar, Jim Irby, Bob Childs, Rejean
Boivin, and Brian
LaBombard from MIT, and Ricky Maqueda from LANL also
participated.
A first meeting of a new density control group took
place last week.
The purpose of the meeting was to open discussion on what
techniques and
hardware will be needed to meet the density control
requirements of AT
operation on C-Mod, particularly during long pulse
operation with LH
current drive.
Experiments to run during the next campaign that would
shed light
on particle control issues were discussed, as were new wall
conditioning
and pumping techniques.
Travel and Visits:
Stewart
Zweben, Les Gereg, and Joe Frangiapani visited from PPPL last
week as
mentioned earlier.
On
January 4th Thomas Pedersen gave a talk at Risoe National Laboratory
in
Denmark entitled "Impurity transport phenomena in the H-mode
transport
barrier region in Alcator C-Mod."