From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
January
17, 2000
Good progress was made on several fronts over the
last week. Work on the
DNB, RF
antennas and transmitters, and invessel activities continued to be
our
primary interests.
Engineering:
The DNB was
operated in its test cell beginning January 7 and continuing
through
January 13. The tests included more
than 200 shots with
varying combinations of power supplies. A neutral beam was generated on a
majority
of shots and at will. The maximum
accelerating voltage attained
for the demand interval of 90 ms was 45
kV. Currents above 4 Amps were
generated
for voltages above 40 kV. The beam is
operating as expected and
is now ready to be installed on C-Mod. This work completes on schedule
another
major DNB milestone.
The boron nitride tiles to be installed on the
E-port antenna have
completed their bake.
They have been stored in our clean room in
a low humidity
atmosphere and will be installed as one of our last
invessel
operations. The J-port antenna is very
nearly complete with only
a few bolts remaining to be installed. Machining of the inner divertor module
for
the new rangefinder view has been completed.
A great deal of work is
still going on in our shop for invessel
components, including parts for
alignment jigs, emissive and flux probes,
CXRS telescopes, the DNB aperture,
pressure sensors, and mirror mounts and
housings.
All four FMIT water systems will be fully assembled and
under test this
week.
Modifications to the FMIT#2 input cavity have been completed and
installed. The 2274 tube recently returned from CPI has
also been installed.
Installation of the output cavity with improved RFI
chokes is in progress.
Work continues on the TMX Power
Supplies. The 15 volt power supplies
have
been tested and are all operating correctly. The interface wiring to
the
new gate boards has been installed and tested. Hi-potting of the SCR
bridges and
testing of the SCR gates continues. The
new gate drive
prototype circuit has been tested in place with only some
minor changes
required. The documentation for the new board is in
progress.
Physics:
Dr. Alan Glasser (LANL) has
provided us with a copy of version 3.10 of his
MHD stability code DCON.
The present version of DCON evaluates the
Mercier criterion D_I > 0 for
unstable localized ideal interchange
modes; the related criterion D_R >
0 of Glasser, Greene, and Johnson for
localized resistive interchange
modes; the criterion C_A < 0 for ideal
MHD ballooning modes in the
limit of large toroidal mode number; the
generalized Newcomb criterion for
the internal ideal MHD stability of
one low toroidal mode number; and the
plasma, vacuum, and total response
matrices and their eigenvalues for
determining free-boundary stability.
A future version of DCON will treat
resistive instabilities. Dr. Glasser will
be working with C-Mod personnel to interface the DCON code to the
MDSplus\
data acquisition and analysis system.
Travel
and Visits:
John Rice attended the JSPF meeting in Sendai from
Nov.23-27 and presented
an invited talk on 'Toroidal Rotation in Alcator
C-Mod Plasmas'. From Nov.27
to Jan.5 he participated in ongoing experiments
at LHD in Toki, and
worked on analysis of the 'Breathing Plasma' with
Byron Peterson.
Stefano Bernabei, Douglas Loesser, Norton Bretz, Bob
Cutler, and Dave Johnson,
all from PPPL, visited MIT last week. Stefano Bernabei and Douglas Loesser
came
to discuss plans for the LH experiment.
Discussions on what ports
to use, how to best implement the
launchers, and scheduling took place.
Norton Bretz and Bob Cutler visited
to bring up the external optics and
electronics for the MSE
diagnostic. They also worked on the
invessel
shutter for this diagnostic as well as a solution to some
interference
problems at the port.
Dave Johnson visited to take some optical components
back to PPPL
for use on NSTX; they are no longer needed for C-Mod.