From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Organization: MIT
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
January
24, 2000
Work continued on the DNB, RF systems, and invessel
work last week.
The invessel work has become particularly important as we
approach
the scheduled mid February pumpdown.
Engineering:
All
work on the DNB in the test lab has been completed, and we have
begun to
move the DNB equipment into the C-Mod cell.
The move is going
smoothly with some major beam components already
moved to the cell.
J-port antenna has been installed. The protection tiles were aligned
without
modifying the tiles. Measurements will
now be taken to
document the antenna location relative to the central
column.
The E-port BN top protection tiles installation preparations have
been
completed. The tiles should
be installed this week.
Modifications to FMIT#2 input cavity and
high voltage connection have
been completed. The input cavity modification is a cut back and
tapering of
the isolation capacitor teflon. The
high voltage
connection modification includes the replacement of two sets
of two
stacked 25 kV capacitors with two sets of 40 kV and 750 pF
capacitors
and 5 uH inductors. The
cavity was successfully hi-potted to 40
kV which is greatly improved over
the previous design. This upgrade
should
allow the transmitter to operate at the highest plate voltage
and
allow higher power operation.
FMIT#1 input cavity has also been
modified. The reassembly has been slowed because of a
broken ferrite
ring. Replacements
have been found and are on order and this delay will
not impact the
overall schedule for restarting C-Mod operations.
Invessel work
included machining of components needed for the reflectometer
invessel
alignment and the CXRS poloidal view telescope. The baking
of numerous components to prepare them for
installation was completed
over the weekend. As mentioned above, work on all three ICRF antennas is
nearly
complete, and RF installations will
present no problem for our
pumpdown schedule.
We continue to
make some upgrades to the bus tunnel and LN2 sump. These
changes will improve the seals and reduce the
possibility of water vapor
penetration into the bus tunnel. The LN2 manifold relief valves have
been
tested and a new manifold added to divert any LN2 that escapes from the
valves
down into the sump. We have also made
some improvements to the heater
system that maintains the vacuum vessel
near room temperature when the
magnets are cooled down to LN2
temperatures. During the last
campaign
water condensation on some of the heater cables made its way into
the
heater connectors and damaged them.
These connectors have all been
checked out, repaired where
required, and covered with a water tight seal.
Travel and
Visits:
Miklos Porkolab attended the 10th International Conference
on Plasma Physics
and Controlled Nuclear Fusion (ITC-10) in Toki, Japan,
January 18-21.
He also was invited to make a special public lecture to the
citizens of Toki
on Saturday, January 22. The title of his 1 hr
presentation was:
"Contribution
of Fusion to Solve the Energy Problem and
the
Environmental Issues in the World"
The
lecture was translated simultaneously into Japanese by Prof. Watari
of NIFS
and the University of Tokyo.
Robert Granetz attended a US/Japan
workshop on MHD stability at high beta,
held at the JAERI Naka site. He presented some of the initial results of
an
MIT-JAERI collaboration on disruption neutral point studies in Alcator
C-Mod.
Presentations from Japan included not just JT-60U, but also the
recently
commissioned Large Helical Device, which apparently has
significantly better
energy confinement than predicted by the
empirically-derived stellarator
scaling law. Detailed studies of Mercier stability (high-k interchange
modes)
are being carried out in LHD, but so far, MHD modes do not limit
confinement
performance. Several
tokamaks (JT-60U, ASDEX-U, TCV) reported that
neoclassical tearing modes
are sometimes seen even for beta_p down to 0.7,
which is within the range
of values that have been achieved on Alcator C-Mod.
Therefore, we should
go back through our MHD data to determine whether or not
such modes have
occurred in our machine.
Steve Wolfe participated in the meeting of
the DIII-D Advisory Committee (DAC)
at General Atomics in San Diego last week. He also continued
discussions
regarding the EFIT code and MDSplus with Lang Lao, Qian Peng,
and
Jeff Schachter.