From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
January
31, 2000
We continued to make good progress on invessel, RF,
and DNB work last
week. Invessel
work has begun to concentrate more or installation
and alignment instead
of fabrication.
Engineering:
Invessel work last
week at K-port included installation and alignment
of the bolo box, and
changes to improve the view of the Z-meter array.
New diborane lines were
also installed. Additional studs have
been
added to better support these lines where they bend out
radially.
The hole pattern in the lines has also been changed to improve
the
distribution of diborane around the machine during boronization.
A
new H-port mirror has been installed to allow the McPherson
VUV
spectrometer view to be scanned across the divertor. Installation of
new flux probes on both limiters is
proceeding. All tiles (fewer than
5)
that showed melting during the last run campaign have been
replaced. All
antenna work is
complete including installation of the new boron nitride
tiles. The new shutter for the MSE diagnostic has
been installed and
made operational. During calibration of the MSE/BES system,
it was discovered
that two of the mirrors in the in-vessel optics
enclosure had come loose, and
the optical system had become misaligned.
These components have gone back
to PPPL where the mount will be
redesigned. The new CXRS poloidal
view
telescope has been installed.
Fabrications still in progress needed for
invessel work include
rangefinder retro-reflector holders, and a new mirror
at A-port. This mirror will provide a new view of the
J-port antenna. These
fabrications should not delay pumpdown. Finally, we have begun to throughly
clean
the vessel to remove old boron deposits.
The input cavity and tube
assembly for the FMIT#1 transmitter is complete
and installed. Work on the output cavity is nearly
complete. We have also
begun work
on modifications to the PPPL demodulators to improve their
response
time.
The DNB was moved from its test area to the C-Mod cell last
week. All major
in-cell components
are in place and interconnection is in progress.
Air, water, and vent
lines are also being installed.
Work continues on upgrades to the
cryo system. We have sealed the
LN2
sump after making improvements to the gas, liquid, and transducer
feedthroughs. Wiring for the cryo control system has also
been improved.
Work to improve the operation of the cryostat exhaust valve
has been planned
and will begin shortly.
Physics:
Recent
analysis of data from the omegatron ion mass spectrometer shows
that the
magnitudes of the resonant ion current increases with applied
RF power up
to a saturation value. A simple model
of the collection
of resonant current reproduces the observations. The model assumes a
shifted
half-Maxwellian distribution for each ion species, allows for
reflection
of ions due to space charge in the resonant cavity, and
establishes a collection
criterion based on resonant ion dwell time in
the cavity. Within the assumptions of the model it is
possible to
extract from the experimental data the temperatures of
individual ion
impurity species.
It is found that the impurity temperatures are all
near the bulk
ion temperature, approximately 3 eV, recorded with the
retarding field
energy analyzer on the omegatron probe.
From the
asymptotic value of the resonant current it is possible to
estimate
the absolute flux of individual impurities. Fluxes of charged states
of boron
dominate the impurities with levels near two percent the
deuterium
flux. With further assumptions about
the relationship
between the impurity velocity and impurity density at the
sheath edge
it is possible to obtain estimates of the impurity density in
the edge
plasma.
Travel
and Visits:
David Winslow and Keith Carter (UT-FRC) spent 1/18 to
1/26 at C-Mod
installing the Texas turbulence probe on the DNB stand at
F-port. The
vacuum system, electronics, and probe alignment work will
begin during the
week of 2/14. It is expected to be ready for operation
during the next
campaign.
Ron Bravenec (UT-FRC) was at C-Mod
from 1/25 to 1/28 to assist Norton Bretz
(PPPL), Dan Simon (PPPL), and
Howard Yuh (MIT) install the relay optics,
PEMs, and image dissector for
the MSE/BES optical system.
Gerd Schilling (PPPL) spent most of last
week at PPPL for discussions on
the
C-Mod collaboration aspects of the PPPL Field Work Proposal.