From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
February
14, 2000
Invessel, RF,
DNB, and power system work continued last week. Pumpdown,
startup of vessel heater and cryo systems, and
leak checking are all
scheduled for the next few days.
Engineering:
The
DNB power systems were brought into operation into the beamline last
week. This operation completes our final milestone
for the DNB approximately
one month early. In addition, a 25 kV beam at approximately 2 amps was
extracted
just to test all the HV, interlock, control, and protection
circuitry. Some ground loop problems were discovered
during the test that
will be fixed over the next few days. We are also in the process of
resolving
DNB personnel safety issues so that people can be allowed in the
cell
during DNB testing. During the first few days of operation we have
not allowed
anyone in the cell when high voltage was applied to the
beamline.
We are moving quickly on invessel work and expect closeup
and pumpdown
this week.
Alignments, invessel cleanup, and documentation and inspections
continue. The new rangefinder retro-reflectors are
installed as are the
tile support plates they look through. The alignment of the new retro-
reflectors
has been checked with a telescope from outside the C-Hor port
and looks
acceptable. Preparations are being made
for alignment of
the tangential two-color-interferometer which will occur
as soon as the
C-Hor flange is back in place. Invessel alignment and calibration of the
visible continuum
array was completed. The input periscope design has been
changed, and the
new system has increased light throughput, which will allow
for improved
time resolution. The system mirror has been slightly reoriented
so that
the camera view goes farther out into the scrape-off, well into
the shadow
of the outboard limiters.
Invessel ICRF antenna activity is complete
including extensive measurements
of antenna tile locations and careful
alignment checks. Measurements of and
possible adjustments to the external resonant loops coupling the antenna
current straps to the transmitters are in progress. One of the loops
for the older D- and
E-port antennas had previously been found to be
off-resonance, and the
recent J-port antenna modifications have
changed its electrical
characteristics sufficiently to necessitate a
recheck. PPPL RF fault detectors in use at C-Mod are
being modified
for faster response times, and remaining transmitter
upgrades are
continuing. A
thermocouple has been added invessel to measure the
temperature of the
E-port antenna with the boron nitride upper and
lower tiles. The #1 and #2 transmitters FPAs, which were
disassembled during
the maintenance period, are nearly back in service, as
checks of the FPA
crowbars have been completed, and tests of the screen
crowbars are
underway.
The MSE optics repair and calibration
will be completed by Tuesday. A lens
assembly motion restrainer will be added from outside the vacuum
vessel
early in the week of 2/14.
We are finishing up work on several
engineering systems in preparation for
vacuum conditioning and eventual
plasma operation. Improvements to
the
GN2 seals on the bus tunnel, cryostat, sump, and valve manifold box
have
been completed. Work on the
heater system to protect the connectors from
water intrusion will be
complete by pumpdown, at which point checkout of the
heaters will begin
with a 35C "bakeout" for a few days. All bus
instrumentation has been refurbished and checked
out. Improvements to
the Cryo
system wiring have been completed.
Calibrations to the 13.8 kV
instrumentation are also nearly
complete. Engineering data is
flowing
again between our control computers (PLCs) and our VaX
cluster.
Physics:
On 2/7 and 2/8 of last week
a Program Advisory Committee Meeting was held
at MIT. Ben Carreras of Oak Ridge chaired the
committee, and the other
members are Philip Efthimion and Ed Synakowski of
PPPL, Ray Fonck of U. of
Wisconsin, Tony Leonard of DIIID, Mike Mauel of
Columbia, and Claude Gormezano
of Frascati. John Willis and Rostom Dagazian from OFES attended the
meeting.
Talks were given by Alcator C-Mod personnel and our collaborators
covering
nearly all aspects of the C-Mod program; the agenda
included:
Welcome --
Porkolab
Introduction and
Overview -- Marmar
Advanced
Tokamak Program:
Goals -- Parker
Modeling --
Bonoli
FY2000 Experiments -- Marmar
Transport:
Overview --
Greenwald
Core Transport -- Rowan
Pedestal Physics -- Hubbard
Divertor/Edge:
Scrape-off Layer Transport -- LaBombard
Long Pulse/AT Divertor
Issues (particle and power) -- Pitcher
ICRF Physics:
Overview --
Wukitch
Heating, Flow and Current Drive -- Schilling
MHD -- Granetz
Performance Enhancements -- Snipes
Schedule and Run Planning -- Wolfe
Experimental Facility Status, Hardware and
Diagnostic Upgrades,
Long Pulse Operation -- Irby
Lower Hybrid RF:
Hardware Plans -- Bernabei
Preparation and Schedule -- Irby
Budget -- Marmar/Keating
In
addition, a session in which questions asked by the PAC were answered
was
held on the second day.
A quarterly review was held on February 9.
Rostom Dagazian from OFES discussed
various aspects of the C-Mod program
with Ian Hutchinson, Earl Marmar, Jim
Irby, Bill Rowan, Dave Terry, Steve
Wukitch, Gerd Schilling and Joel Hosea.
The discussions centered on the
status and near term plans for the diagnostic
neutral beam and its
associated diagnostics, and on the ICRF systems.
Travel and
Visits:
Barrett Rogers of U Md visited to deliver a seminar on
edge
turbulence. Discussions with
members of the C-Mod team included
future plans for collaboration on
non-linear fluid simulations and
gyro-kinetic stability
calculations.
Joel Hosea, PPPL,
came 2/7-2/9 to discuss Lower Hybrid program issues and
our coming
ICRF startup. Stefano Bernabei also
came from PPPL to participate
in LH program discussions (as well as give a
talk at our PAC meeting).
Rejean Boivin was in Quebec city for the
first (on site) planning meeting
for the APS-ICPP meeting in next october.
Plans were made for the
outreach day and space allocation.