From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Organization: MIT
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
February
22, 2000
The Alcator C-Mod up-to-air period ended on Thursday,
2/17, with pumpdown
of the vessel.
The ICRF transmitters are coming back online. The
cryostat is being purged with nitrogen gas in
preparation for cooldown.
Engineering:
After
completing the last installations, final alignments, extensive
documentation,
including 35 mm pictures, video, and digital photographs,
and a final wipe
down of exposed surfaces, Alcator C-Mod was pumped
down last
Thursday. Leaks caused by an improperly
installed flange
and window were fixed on Friday and the vessel has now
pumped down to
a level at which useful helium leak checking can be
done. On Friday we
also verified
operation of the cell and power room oxygen alarms, and
then began the GN2
purge of the cryostat, bus tunnel, and magnets. The
humidity detectors in the GN2 line and cryostat
indicated rapid removal
of water vapor from the cryo system. We will be able to begin cooldown
of
the machine with liquid nitrogen as soon as the moisture level falls
below
10 ppm. The process of bringing the
vessel heaters back online
was also begun. A low temperature bake (60 C) of the machine is expected to
begin
this week as soon as all these systems have been carefully checked
for
proper operation and the vessel has been verified to be leak tight.
The
vacuum connection between C-Mod and the DNB was completed. This process
was coordinated with other
activities at F-port including installation of
toroidal CXRS optics,
installation of an additional lens support for the
MSE/BES optics,
installation of waveguide and RF mixer stand for the FRC-ECE
system, and
alignment of the FRC turbulence probe.
The J-port antenna electrical
characteristics have been measured.
The
invessel changes made to the J-port antenna current straps had
significantly
changed the electrical characteristics of the antenna. Modifications
to the loop configuration
will begin this week.
FMIT#1 and #2 have been tested into a dummy
load at up to 2.5 MW without
approaching the tube limits (anode
dissipation, anode current, screen
dissipation, screen current, grid dissipation,
grid current). We will
begin
commissioning and testing FMIT#3 and #4 into a dummy load this
week.
We
have completed a modification to the RF demodulator modules used in the
RF
data aquisition system. These modules
still need power supply upgrades
and re-calibration. A system test of the RF protection
circuitry
will begin this week.
Finally, a partial list of
invessel work during this up-to-air
period includes:
- addition
of a visible TV view of the entire J-port antenna
- new flux probes on two
limiters
- new emissive probes on one limiter
- improved TTCI mirror
housing
- neutral pressure gauges (5 locations) near the plasma
-
refurbished (cleaned) D and E antenna
- designed, fabricated, and
installed boron nitride tiles for E antenna
- added 3 additional
retroreflectors for inner wall rangefinder measurements
- added MSE
shutter (PPPL and Texas)
- refurbished mirror and lens supports for MSE
(PPPL and Texas)
- added 2nd set of fibers for tangential edge CXRS
(Texas)
- added edge poloidal view for CXRS
- refurbished mirror
assembly for McPherson spectrometer
- modified J port antenna to eliminate
impurity injections (with PPPL)
- added 2nd Lyman alpha view (inner
wall)
- added protective cover over H-port flux loop
In
addition, we performed routine maintenance on:
- tiles
-
telescopes and periscopes
- limiters and protection tiles
- all
flappers
- various gate valves
- many system pumps
- invessel
thermocouples
we also
- cleaned and calibrated fibers for
core CXRS (Texas)
- calibrated views and refurbished fiber optics for
several invessel systems
- completed the neutron calibration
-
calibrated the reflectometer
- calibrated Z meter array alignment
-
aligned TTCI
- did complete wipe down of vessel walls to remove old boron
deposits
and associated
compounds
Travel and Visits:
Norton Bretz visited
from PPPL to complete work on the MSE diagnostic.
Gary Taylor, PPPL,
visited MIT 2/15-17 to remount the GPC2 electronics in a
radiofrequency-shielded
enclosure to suppress rf pickup from the J-port
ICRF antenna and to
discuss electronics upgrades with Amanda Hubbard.
UT-FRC personnel
visiting to complete diagnostic installation work last week
included Keith
Carter, Perry Phillips, and David Winslow.