From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
Feb
28, 2000
Preparation for the next C-Mod experimental campaign
continued last week. We
are on schedule to begin plasma operations during
the last week in March.
Initial (pre-bake) evaluation of the vacuum
status is good, with no detectable
leaks remaining as of Thursday. A
high-temperature bakeout commenced on Friday,
with the vessel held at 100C
through Monday morning. The bake temperature has
now been increased to
110C; the high-temperature bake is planned to continue
through the end of
this week.
While the vessel is undergoing bakeout, the magnet and
structure temperatures
are being maintained at reduced temperature (<
-50C) by LN2 cooling. The
cryogenic system is now fully operational.
The
PEI supply, which powers the Toroidal Field magnet during Electron
Cyclotron
Discharge Cleaning (ECDC) has been tested and is ready for
operation. ECDC
is expected to begin this week.
The diborane cabinet has been
relocated from the cell to the vestibule under
the bus tunnel. The exhaust
and air lines have been installed. Work on this
system is
continuing.
ICRF Systems:
--------------
The 78 MHz
resonant loops for [0,pi,0,pi] phasing have been tested and the
decoupler
measured. The current drive loop
measurements will be completed
this week.
The antenna protection system time response has been reduced to 5
usec. This system monitors the ratio of
reflected/forward power, the maximum
voltage, and the antenna current
balance.
The transmitters FMIT#3 and #4 were each tested into dummy
load up to 2.1 MW
with good characteristics. Longer pulse (~1 sec) under remote control testing
will
begin this week.
DNB
---
Good progress was made on the
diagnostic neutral beam system. Wiring
modifications to the DNB Master
Control Logic timing circuits to allow remote
setting of important timing
parameters and synchronization with the CMOD shot
cycle were
completed. The DNB timing software was
changed for compatibility
with the modified MCL timing circuits, and the
DNB Conditioning software and
modified DNB MCL timing circuits were tested
successfully. Arcdown interrupt
response
of the modified DNB MCL timing circuits was also tested successfully.
Travel
and Visitors
--------------------
Miklos Porkolab represented APS DPP
at the EPS Program Committee Meeting in
Budapest, Hungary, on Feb. 25,26.
Four more US oral talks were selected for
the EPS Meeting in Budapest, on
June 12-16. This brings up the total number of
US presentations to 10, out
of a total of 56 talks, including 6 US invited
talks and 4 oral
contributed talks. This is a respectable representation at
this mainly
European Meeting on Plasma Physics and Fusion research. This year
the goal was to keep half of
the talks non-fusion oriented.
Therefore, the
available fusion slots were highly contested by the
many more nominations from
Europe, the US and Japan.