From: WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT



            Alcator C-Mod Weekly Highlights
                        March 13, 2000
                        

Alcator C-Mod is now undergoing ECDC conditioning of the vessel wall.
ECDC will be in operation more or less 24 hours a day over the next two
weeks as we prepare for plasma startup.  Work continues on the RF
and DNB systems, and diagnostic installation.


Engineering:
-----------
ECDC was begun last Tuesday.  Cleanup of the vessel surfaces has been
going well, with our primary interest being the the reduction of water
and hydrogen in the machine.  The light from the ECDC has also been useful
for testing and aligning new TV views of the antennas.

The alternator came back online this week.  It was brought up to half
speed on Wednesday, vibration levels were checked, and all systems
were checked for proper operation.  New signals monitoring the exciter
supply have been added to the CAMAC system.

The diborane system has been moved from under the diagnostic stand to
the cell entry vestibule.  This change gives much better access to the
diborane cabinet while also freeing up valuable real estate near the
machine.  Re-routing of control cables, gas lines, and vents was
required.

DNB
---

 All filament and arc supply gate and voltage regulator boards were
tested and adjusted as required for proper regulation in dummy loads.  Gate
block circuits were added to all filament supplies to block gates if
the setpoint is below a couple of volts;  all were tested successfully.
Smoothing capacitors were tested on filament 2 supply with marked
improvement in ripple.  We will be adding these capacitors to each of the
four filament supplies.

The filament cables and connectors were inspected, and problems identified by
testing with 100A at 10V. The filaments were characterized and
documented. Parallel cables were added for the longest straight run of
filament cabling, to reduce the voltage drop, and the tests were repeated. The
data are being analyzed to evaluate the improvement.

ICRF:
-----

We completed modifying the resonant loops on D and E-port to move the feed
point to a high voltage point.  This required shortening the 36" probe section
to 17.3" and 12.5" for D and E-port, respectively.  Impedance measurements
indicate that loop lengths correspond to 80.1 MHz and 80.3 MHz for D and
E-port, respectively.  During the disassembly process, E-port feedthru #3
(numbered from top of the port down) was found to have a loose center
conductor connection.  It had arc damage and required a rebuild.  We made
measurements so that a single piece could be made to eliminate this assembly
problem.

Transmitter tuning and testing is being repeated due to identification of a
calibration error in the diagnostics used in tuning the transmitters.  We have
requested RF engineering support from PPPL and expect C. Brunkhorst to visit
this week.



Physics:
--------
The TCI interferometer is back in operation.  Changes have been made to the
plasma arm to allow measurements to be made somewhat farther out in major
radius.  The radial coverage has also been reduced to increase the
radial resolution on the outer channels.  These changes also allowed nearly
3 meters of optical pathlength together with several large mirrors and mounts
to be removed from the plasma and reference arms which should
improve alignment stability.

The new visible TV view of the E-port antenna is operational.

Gerd Schilling continued work on the C-Mod collaboration Field Work
Proposal, and prepared the C-Mod contribution to the US - Japan RF
Workshop to be held at PPPL March 14-16.

Visitors and Travel
--------------------

Bruce Lipschultz traveled to JET to participate in US-JET collaboration
discussions held March 7-9. He was part of a group representing the
different US laboratories as well as particular physics areas. Bruce
collected from US labs proposals for work on edge physics for JET for
2001-2002. The meeting was very helpful for understanding the JET program
and their plans. The JET task force leades expressed strong interest in a
number of US proposals including those from MIT.
     
Bruce also spent part of 3/9 and 3/10 discussing a number of physics issues
with the JET edge/divertor group. These discussions centered around
similarities between C-Mod and JET in the area of wall-recycling. He brought
back some typical JET data for comparison with C-Mod results. He also gave 2
presentations - SOL transport and wall recycling, and Mo impurity sources and
their effect on the core plasma.