From: IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT



            Alcator C-Mod Weekly Highlights
                        March 20, 2000
                        

Work continued last week on the Lower Hybrid, ICRF, DNB, and Power systems.
We are now beginning pre-operations checkouts on all the major machine systems
in preparation for power supply tests into the magnets scheduled to begin
this week.  ECDC continued all week to prepare plasma facing components
for operation.


Engineering:

The klystron test stand is coming together rapidly.  Wiring of the
Modulator/Regulator for the klystron is nearly complete.  Power has been
applied to the control rack and testing has begun.  Fabrication and wiring
is complete on the transmitter protection system (TPS).  The first klystron
to be tested has been loaded into the test stand socket and water cooling
lines have been connected.  The high voltage control rack wiring is complete.
The high voltage power supply is ready to be wired into the test stand
and checked out.  Components from the Alcator C lower level 4.6 GHz RF
system have been checked out and those useful for the new system identified.

On Thursday and Friday of last week we changed the bus configuration from
normal to reversed field.  We are starting out with reversed field this
campaign so that the initial startup time time can be combined with
development of a robust reversed field startup.  Other work on the power
systems included a general cleanup of the bus and cabinets, the addition
of four new signals to better instrument the alternator exciter supply, and
re-calibration of hi-yard current and voltage monitors.

A new set of digitizers has been installed in the magnetics rack.  We hope
these new units will improve the reliability of the magnetics signals which
were on some occasions lost because of CAMAC problems during previous
campaigns.

Work continued on the DNB last week.  To obtain somewhat more filament
current the filament bus leads were increased in size and the filament
power supply was adjusted for maximum voltage.  Low filament current
had been limiting the filament emission during DNB operation in the
Cell.  The DNB will operate with the C-Mod shot cycle this week during
power tests.

We continue to bring up the ICRF systems for the next campaign.  Vacuum
conditioning of the antennas should begin this week.  During his visit
last week Chris Brunkhorst gave us the spreadsheet he uses for tuning
the PPPL transmitters.  Using this program has allowed us to improve the
tuning of all the transmitter stages.  FMIT#3 is the only transmitter
awaiting final tuning.  


Physics:

Calibration of the integrator circuits for the main magnetics signals
indicated systematic changes in the time constants in the range of
1-3% (over the past five years), with higher gain (lower RC) circuits
exhibiting the bigger changes.  The effect of applying the revised
calibrations to EFIT analysis of several shots from the last campaign was
evaluated. Use of the new values moves the outboard midplane location of
the LCFS in by 2-3mm relative to the uncorrected analysis; the change in
the inferred boundary is largest at the outboard side near the midplane,
and essentially vanishes near the x-point and on the inboard side.  These
results tend to bring the EFIT reconstructions into somewhat better
alignment with edge diagnostics such as the A-side scanning probe,
although discrepancies of 3-5mm remain unaccounted for.

A new head for the A-side fast scanning probe is being made with a poloidal
field pick-up coil mounted inside the probe head so that it will be very near
the plasma at full insertion.  The probe head will be made from boron nitride
to allow high frequency field fluctuations to penetrate to the coil.  The coil
is about the size of a pencil eraser and is ceramic coated nickel-clad copper
conductor wound onto a boron nitride spool.  The coil will be positioned about
9 mm back from the tip of the probe.  We expect the new head to be close
enough to measure the 100 kHz fluctuations that are observed in EDA H-mode on
the Langmuir probes, reflectometer, and PCI diagnostics. 
Being within about one wavelength of the pedestal, magnetic fluctuations, if
present, will be observable on the magnetic pick-up coil. The oscillations are
localized in the density pedestal and k_r is measured to be approximately
5 cm^-1. A mode with properties like the one observed has been seen in
electromagnetic gyrofluid simulations by Rogers and Drake. The modes seen in
the simulations have a significant magnetic component, so this coil should
provide an important experimental test of the theory.  The coil has already
been made and absolutely calibrated.  The coil area is about one third of the
area of the existing pick-up coils mounted on the outboard limiters.
Initially, the probe will be inserted into Ohmic EDA H-modes to avoid the
higher heat flux associated with RF heated H-modes and allow deeper
penetration of the probe.  In a second stage, the probe will be inserted
into RF EDA H-mode to also look for the high frequency (~600 kHz) modes
observed on the outboard limiter pick-up coils to determine their radial
decay and whether or not they are resonant at the edge of the plasma.

Last week the physics meeting was broadcast using RealPlayer
( http://www.real.com ) streaming video.  This technology  gives
collaborators access to the meeting using standard WWW tools.
Tune in to future meetings with RealPlayer at

      rtsp://www.psfc.mit.edu/encoder/nw17.rm


Travel and Visits:

Chihiro Takahashi from the NIFS in Japan visited Tom Fredian and Josh
Stillerman to discuss the use of MDSplus on the CHS experiment. They hope to
migrate from their current data system completely to MDSplus by the end of
this year.

Miklos Porkolab attended the US-Japan RF Workshop in Princeton,
on 3/14/2000.  Paul Bonoli also attended (3/14-3/16) and gave a talk
entitled "Advanced tokamak physics studies in the Alcator C-Mod device".
He also spent one day working with PPPL staff on full-wave ICRF modelling
of high harmonic fast wave heating in the NSTX device.

Chris Brunkhorst, from PPPL,  was at MIT from 3/14-17 and helped with the ICRF
transmitter tuning and checkout in preparation for the next run campaign.
Gerd Schilling spent last week at PPPL, finishing the C-Mod
collaboration Field Work Proposal and presenting the C-Mod
contribution to the US-Japan RF Workshop, March 14-16, "Upgrades and
Recent Results from the Alcator C-Mod ICRF Program."