From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: MIT
Alcator C-Mod Weekly
Highlights
March 27, 2000
The C-Mod power supplies were
tested into the machine last week.
We
are in the final preparation stages for the start of the next
run period.
Work continued on the Lower Hybrid test stand, ICRF
transmitters, and the
DNB. Work is
moving forward on the new divertor upgrade.
Engineering:
On
Monday of last week C-Mod was pre-cooled to standard between run
temperatures. On Tuesday a full cooldown took place and
power supply tests
into the magnets were begun. All supplies were tested during this first
day, as well as
the pulsed gas system. On Tuesday tests
of the
commutation banks were completed and a plasma attempt was
made. H-alpha,
CII, visible
bremsstrahlung, and magnetics diagnostics indicated an initial
breakdown
with a good null. We then stopped
operation for the rest of the week
so that work on the ICRF and DNB
systems, which require power room access,
could continue. Operation will begin again this Tuesday with
investigation
of reversed field startup optimization being the primary
goal. The week will
also be used
for diagnostic commissioning and checkout.
The DNB was operated into
its beam dump at up to 47 kV.
Repeatable 100ms
pulses were created at 45 kV with 5.2 A of beam
current. The arc current
as a
function of filament current was re-characterized with the longer cables
into
the C-Mod cell. Operation of the beam
in the C-Mod cell had
previously been limited to 20 kV by arcing between
the accel and gradient
grids. This
problem was traced to the initial voltage rise of the grids
which caused
the two grids to be more than 16 kV apart (normal operation
has a 5 kV
spacing at 50 kV). The problem was
fixed by adding additional
capacitance to the gradient grid voltage
divider and by adjusting the
mod-reg rise time. The accel and gradient grid voltage rises were
characterized
as a function of mod-reg parameters.
We continued work on the Lower
Hybrid test stand last week with the
installation and wiring of some of
the crowbar components. Work on
the
high voltage bus was also started.
The low voltage power supply for the TPS
(Transmitter Protection
System) chassis is operational, assembly of
the TPS cards is complete, and
the cards have been powered up. Testing
of
the TPS control functions has begun.
The high voltage control wiring
installation is in progress, and
work on the water cooling system continues.
As part of the divertor
upgrade project, a detailed 3D computer model of the
C-Mod vacuum vessel
is being produced with locations of studs, thermocouples,
and magnetics
indicated. A design for the new divertor incorporating a
re-enforcing hoop
that both supports the tiles and adds strength to the inner
wall is also
being developed. A non-linear
finite-element-analysis of the
new design is being carried out, and the
response of the new hardware to
halo and eddy currents generated during
disruptions is being quantified.
Installation
of these new components is planned for our next up-to-air period.
Physics:
N.
Bretz and R. Cutler, PPPL, worked at
C-Mod from 3/20-3/23 this week with
H. Yuh of MIT installing the MSE and
BES image dissector and the photoelastic
modulator, installing the shutter
control, referruling the BES fibers, and
installing the MSE and BES fibers
in the dissector at F-Port. The
MSE
fibers were checked and connected to their respective photomultpliers
in
the rough setup lab and a filter set was installed which will match
operations
with a 45 keV hydrogen beam and a 5.3 Tesla on-axis toroidal
field.
All of the electronics on the test cell floor and in the rough
setup lab were
connected. The
filter heater controls were tested though CAMAC and appear to
be
working. H. Yuh is completing the I/O
controls and MDSplus tree.
This work completes virtually all of the
hardware installation for MSE and
integrates the BES fibers into the
combined dissector.
Travel and Visits:
Dr.
Nakanishi Hideya and Dr. Emoto Masahiko from the LHD experiment at NIFS
visited
Tom Fredian and Josh Stillerman from 3/20-3/24 to discuss data
acquisition
and analysis topics, including new data acquisition hardware,
MDSplus
porting status, CCD camera applications and data handling, and data
visualization
tools.
Bill Noonan and Ray Elton, from the U. of Maryland, were here
last week to
prepare their spectrograph for operation during the next run
campaign.